Preliminaries - Cryostat intervention [[Continuum/NIKA2/Main|Back to the NIKA2 main page]]
Line 3: Line 3:
According to the discussion summarised [[https://publicwiki.iram.es/NextIntervention202506|here]], = Cryostat intervention (June 2-4, 2025) =

According to the decisions taken during the April 11th meeting (see the minutes [[https://publicwiki.iram.es/NextIntervention202506|here]]), the next intervention aims to replace the array 2/box C LNA. It is provided to do that on June 3rd.

== Participants ==

Alessandro, Martino, Dave, Angel

== Overall schedule ==

* End of May: NIKA2 warm-up

* June 2nd: Alessandro, Martino & Dave arrive to the telescope. First disassembling operations?

* June 3rd: Access 4K stage. Change the corresponding amplifier. Put back the screens. Vacuum pumping. Start cooling down.

* June 4th (daytime): Reserved as a backup.

[[DailyReportsNika2Upgrade2025_2 |Daily Reports]]

Back to the NIKA2 main page

Cryostat intervention (June 2-4, 2025)

According to the decisions taken during the April 11th meeting (see the minutes here), the next intervention aims to replace the array 2/box C LNA. It is provided to do that on June 3rd.

Participants

Alessandro, Martino, Dave, Angel

Overall schedule

* End of May: NIKA2 warm-up

* June 2nd: Alessandro, Martino & Dave arrive to the telescope. First disassembling operations?

* June 3rd: Access 4K stage. Change the corresponding amplifier. Put back the screens. Vacuum pumping. Start cooling down.

* June 4th (daytime): Reserved as a backup.

Daily Reports