Cryostat intervention (June 2-4, 2025)
According to the decisions taken during the April 11th meeting (see the minutes here), the next intervention aims to replace the array 2/box C LNA. It is provided to do that on June 3rd.
Participants
Alessandro, Martino, Dave, Angel
Overall schedule
* End of May: NIKA2 warm-up
* June 2nd: Alessandro, Martino & Dave arrive to the telescope. First disassembling operations?
* June 3rd: Access 4K stage. Change the corresponding amplifier. Put back the screens. Vacuum pumping. Start cooling down.
* June 4th (daytime): Reserved as a backup.