NIKA run #2 (13. - 25. Oct 2010, week 42)

Back to the NIKA main page

2nd test run of NIKA at the IRAM 30m telescope


/!\ Edit conflict - other version:


Test run plan: 14.10. - 25.10.2009

Telescope Schedule


/!\ Edit conflict - your version:


Test run plan: 14.10. - 25.10.2009

Telescope Schedule


/!\ End of edit conflict


#

Dates

Main Task

Details

Lead (IRAM/Neel)

Support

13.10.

Arrival of first visitors in Granada

14.10. Thursday

Arrival of truck, mount and cool down

Limited access to Rx-Cabin: 4 hours in afternoon

Samuel/Alain

15.10. Friday

Cool down / system checks

Limited access to Rx-Cabin: 2 hours in afternoon

Samuel/Alain

16.10. Saturday

Optical alignment (incl. removal of M3)

Limited access to Rx-Cabin: 2 hours in afternoon

Samuel/Alain

17.10. Sunday

Bright sources optical model

Limited access to Rx-Cabin: 2 hours in afternoon

Clemens/Alain

18.10. Monday

Observations T16-10

6h30 - 20h30

Samuel/Alain

19.10. Tuesday

Observations T16-10

17h30 - 2h30

Samuel/Alain

20.10. We. - 21.10 Th.

Observations T16-10

14h30 - 2h30

Samuel/Alain

22.10. Friday

Observations T16-10

9h00 - 21h00

Samuel/Alain

23.10. Saturday

Observations T16-10

18h00 - 6h00

Samuel/Alain

24.10. Sunday

Observations T16-10

14h30 - 2h30

Samuel/Alain

25.10.

Warm up, dismount

Free Rx cabin for 11h00


/!\ Edit conflict - other version:


htm page of the Run schedule


/!\ Edit conflict - your version:



/!\ End of edit conflict



/!\ Edit conflict - other version:



/!\ Edit conflict - your version:


htm page of the Run schedule


/!\ End of edit conflict


Staffing of the test run (DRAFT by CK, 2.9.2010)

The total number of rooms at the Pico is 14.


/!\ Edit conflict - other version:


htm page of the NIKA staff schedule


/!\ Edit conflict - your version:


htm page of the NIKA staff schedule


/!\ End of edit conflict


NOT DEFINITIVE YET (uncertain dates in pastel colors)

List of astronomical target (DRAFT by FXD, 3.9.2010)

ListAstroTarget