NIKA run #2 (13. - 25. Oct 2010, week 42)

Back to the NIKA main page

Test run plan: 14.10. - 25.10.2010

Telescope Schedule

#

Dates

Main Task

Details

Lead (IRAM / Neel)

Support

13.10.

Arrival of first visitors in Granada

14.10. Thursday

Arrival of truck, mount and cool down

Limited access to Rx-Cabin: 4 hours in afternoon

Samuel / Alain

15.10. Friday

Cool down / system checks

Limited access to Rx-Cabin: 2 hours in afternoon

Samuel / Alain

16.10. Saturday

Optical alignment (incl. removal of M3)

Limited access to Rx-Cabin: 2 hours in afternoon

Samuel / Alain

17.10. Sunday

Bright sources optical model

Limited access to Rx-Cabin: 2 hours in afternoon

Samuel / Alain

18.10. Monday

Observations (T16-10)

6h30 - 20h30

Samuel / Alain

19.10. Tuesday

Observations (T16-10)

17h30 - 2h30

Samuel / Alain

20.10. We. - 21.10 Th.

Observations (T16-10)

14h30 - 2h30

Samuel / Alain

22.10. Friday

Observations (T16-10)

9h00 - 21h00

Samuel / Alain

23.10. Saturday

Observations (T16-10)

18h00 - 6h00

Samuel / Alain

24.10. Sunday

Observations (T16-10)

14h30 - 2h30

Samuel / Alain

25.10. Monday

Warm up, dismount

Free Rx cabin for 11h00 (MAMBO-2 operations)

color table of the Run schedule

Staffing of the test run (DRAFT by CK, 2.9.2010)

The total number of rooms at the Pico is 14.

  • IRAM/Granada (9 rooms minimum during the week, 7 rooms at weekends):
    • Operators: J.L.Santarén (day time), F.Damour (night time) (2 rooms)
    • J.Penalver (1 room, Mon-Wed), S.Sanchez (Wed-Fri)
    • Astronomers of Duty / Friend of the instrument: D.Riquelme or G.Quintana-Lacaci (1 room)
    • Receiver group: Dave John or Santiago Navarro ? (1 room)
    • Computer group: Walter Brunswig or Albrecht Sievers ? (1 room)
    • Additional 2 rooms are the minimum needed for cooks and cleaning personal.
  • IRAM/Grenoble: Samuel Leclercq or Markus Roesch or Robert Zylka or Karl Schuster ? (2 at a time, 2 rooms)
  • Visitors from Neel, LAOG, AIG Cardiff, SRON Utrecht, Groningen: *upto 4 rooms during the week* may be used by the visitors. Double occupancy is an option, but the cooks would need to be informed beforehand of this extra load. If more visitors are essential, they'd need to stay over night in the nearby ski resort Pradollano, e.g. at the hotel Kenia.

color table of the NIKA staff schedule

List of astronomical target (DRAFT by FXD, 3.9.2010)

ListAstroTarget

Above information plus more details (logistics, preparation of the run, sources list) on the following pdf document

Test plan 2010 10 (updated 14 Oct 2010)

Daily reports

Thursday, Oct 14

  • Everybody has arrived at the telescope, Computer and network installation in the control room done, electrical connection of the instrument checked, NIKA is ready to be lifted to the receiver cabin.