Cryostat intervention

According to the decisions taken during the April 11th meeting (see the minutes here), the next intervention aiims to replace the array 2/box C LNA. It is provided to do that on June 3rd (Wed. 4th over daytime period is reserved as a backup).

Participants

Alessandro, Martino, Dave, Angel

Overall schedule

* End of May: NIKA2 warm-up

* June 2nd: Alessandro, Martino & Dave arrive to the telescope. First disassembling operations?

* June 3rd: Access 4K stage. Change the corresponding amplifier. Put back the screens. Vacuum pumping. Start cooling down.

* June 4th (daytime): Reserved as a backup.