Size: 712
Comment:
|
Size: 728
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 1: | Line 1: |
= Cryostat intervention = | = Cryostat intervention (June 2-4, 2025) = |
Line 3: | Line 3: |
According to the decisions taken during the April 11th meeting (see the minutes [[https://publicwiki.iram.es/NextIntervention202506|here]]), the next intervention aiims to replace the array 2/box C LNA. It is provided to do that on June 3rd. | According to the decisions taken during the April 11th meeting (see the minutes [[https://publicwiki.iram.es/NextIntervention202506|here]]), the next intervention aims to replace the array 2/box C LNA. It is provided to do that on June 3rd. |
Cryostat intervention (June 2-4, 2025)
According to the decisions taken during the April 11th meeting (see the minutes here), the next intervention aims to replace the array 2/box C LNA. It is provided to do that on June 3rd.
Participants
Alessandro, Martino, Dave, Angel
Overall schedule
* End of May: NIKA2 warm-up
* June 2nd: Alessandro, Martino & Dave arrive to the telescope. First disassembling operations?
* June 3rd: Access 4K stage. Change the corresponding amplifier. Put back the screens. Vacuum pumping. Start cooling down.
* June 4th (daytime): Reserved as a backup.