Line 3: Line 3:
According to the decisions taken during the April 11th meeting (see the minutes [[https://publicwiki.iram.es/NextIntervention202506|here]]), the next intervention aiims to replace the array 2/box C LNA. It is provided to do that on June 3rd (Wed. 4th over daytime period is reserved as a backup). According to the decisions taken during the April 11th meeting (see the minutes [[https://publicwiki.iram.es/NextIntervention202506|here]]), the next intervention aiims to replace the array 2/box C LNA. It is provided to do that on June 3rd.

Cryostat intervention

According to the decisions taken during the April 11th meeting (see the minutes here), the next intervention aiims to replace the array 2/box C LNA. It is provided to do that on June 3rd.

Participants

Alessandro, Martino, Dave, Angel

Overall schedule

* End of May: NIKA2 warm-up

* June 2nd: Alessandro, Martino & Dave arrive to the telescope. First disassembling operations?

* June 3rd: Access 4K stage. Change the corresponding amplifier. Put back the screens. Vacuum pumping. Start cooling down.

* June 4th (daytime): Reserved as a backup.