| According to the discussion summarised [[https://publicwiki.iram.es/NextIntervention202506|here]], | According to the decisions taken during the April 11th meeting (see the minutes [[https://publicwiki.iram.es/NextIntervention202506|here]]), the next intervention aiims to replace the array 2/box C LNA. It is provided to do that on June 3rd (Wed. 4th over daytime period is reserved as a backup). == Participants == Alessandro, Martino, Dave, Angel == Overall schedule == * End of May: NIKA2 warm-up * June 2nd: Alessandro, Martino & Dave arrive to the telescope. First disassembling operations? * June 3rd: Access 4K stage. Change the corresponding amplifier. Put back the screens. Vacuum pumping. Start cooling down. * June 4th (daytime): Reserved as a backup. [[DailyReportsNika2Upgrade2025_2 |Daily Reports]] |
Cryostat intervention
According to the decisions taken during the April 11th meeting (see the minutes here), the next intervention aiims to replace the array 2/box C LNA. It is provided to do that on June 3rd (Wed. 4th over daytime period is reserved as a backup).
Participants
Alessandro, Martino, Dave, Angel
Overall schedule
* End of May: NIKA2 warm-up
* June 2nd: Alessandro, Martino & Dave arrive to the telescope. First disassembling operations?
* June 3rd: Access 4K stage. Change the corresponding amplifier. Put back the screens. Vacuum pumping. Start cooling down.
* June 4th (daytime): Reserved as a backup.