second intervention on dichroic and Ar2 shims to try compensating 2mm-1mm focus difference since last intervention

Work Plan

Extracted from July 15 regular NIKA2 meetings with few more details:

Preliminary work before September 14th, 2026, and staff for the intervention

Intervention team: Martino Calvo, Benedetta Kalemi, Samuel Leclercq, David John

All the team at the telescope on Monday 14th, to prepare everything for the intervention on Tuesday morning.

September 15th, Tuesday

Opening NIKA2:

260915_1_Dismounting_NIKA2_nose 260915_2_Dismounting_NIKA2_nose 260915_3_Dismounting_NIKA2_nose 260915_4_Dismounting_NIKA2_nose 260915_5_Dismounting_50K-stage-nose-height-adjustment-tie-rods 260915_6_Unlocking_300K_stage_to_slide_it 260915_7_100K_screen 260915_9_4K_screen 260915_10_1K_screen 260915_11_NIKA2_100mK_stage

Opening of the cryostat quite efficient, done in a bit more than 2 hours.

260915_14_Measuring_dichroic_distance_to_mount-top-face_Rx-cabin-side 260915_15_Measuring_dichroic_distance_to_mount-top-face_center 260915_16_Measuring_dichroic_distance_to_mount-top-face_Vertex-cabin-side

==> The dichroic is distorted by 2.0 mm, exactly the distortion deduced from the Ar3-Ar2 = 1.2 mm focus difference obtained in the focus test done during the summer vacations.
We dismount completely the dichroic and let the free membrane relax for 7 hours.