Back to the NIKA2 main page

Back to NIKA2 run 72 (Cryo run 84) main page

Plan for the NIKA2 re-commissioning (March 18th to 25th + March 30th to April 1st, 2025)

See also the minutes of the 2025/01/24 meeting dedicated to the re-commissioning (at the difference of the minutes, which describe things as they were discussed during the meeting, the test plan below, originally extracted from these minutes, may contain few differences resulting from upgrades depending on possible evolution of the hardware situation and new information since the meeting. So please refer to this test run page for the actual plan that the re-commissioning team will follow (in principle differences should be marginal).

Originally, two weeks were booked for the re-commissioning. The plan was to quickly assess the relative focus between the three arrays and decide if we need to re-open in order to move the arrays and bring them to the same focus position (as much as possible).

The re-commissioning has now been reduced to one week in march and a second week at a later time, possibly at the end of May or beginning of June. In fact we realised that warming up takes 5 days, cooling down takes ~one week, and therefore re-opening the cryostat to move the arrays would occupy more than one week and we would have had no time for the second part of the re-commissioning (after the 2nd opening).

Participants

(preliminary)

On site: Angel, Stergios, Stefano, Carsten, Juan Macias-Perez (to be confirmed)

Remotely: Nicolas (except 18/3 @ 17 and 21/3 in the evening), Xavier (20-24/3), Samuel, Alessia (18-21/3)

Brisa is warned of the chance of using EMIR if anything goes wrong with NIKA2

Overall schedule

Detailed operations