Plan for the NIKA2 re-commissioning, after the March 2025 upgrade

See also the minutes of the 2025/01/24 meeting dedicated to the re-commissioning.

Originally, two weeks were booked for the re-commissioning. The plan was to quickly assess the relative focus between the three arrays and decide if we need to re-open in order to move the arrays and bring them to the same focus position (as much as possible).

The re-commissioning has now been reduced to one week in march and a second week at a later time, possibly at the end of May or beginning of June. In fact we realised that warming up takes 5 days, cooling down takes ~one week, and therefore re-opening the cryostat to move the arrays would occupy more than one week and we would have had no time for the second part of the re-commissioning (after the 2nd opening).

Overall list of operations (see detailed list below)