See also the minutes of the 2025/01/24 meeting dedicated to the re-commissioning. | See also the [[https://wiki.iram.fr/wiki/nika2/images/d/dd/Minutes_NIKA2_recommissioning_meeting_20250124.pdf|minutes]] of the [[https://wiki.iram.fr/wiki/nika2/index.php?title=NIKA2_upgrade_re-commissioning_preparation_2025|2025/01/24 meeting dedicated to the re-commissioning]]. |
Back to NIKA2 run 72 (Cryo run 84) main page
Plan for the NIKA2 re-commissioning (March 18th-25th, 2025)
See also the minutes of the 2025/01/24 meeting dedicated to the re-commissioning.
Originally, two weeks were booked for the re-commissioning. The plan was to quickly assess the relative focus between the three arrays and decide if we need to re-open in order to move the arrays and bring them to the same focus position (as much as possible).
The re-commissioning has now been reduced to one week in march and a second week at a later time, possibly at the end of May or beginning of June. In fact we realised that warming up takes 5 days, cooling down takes ~one week, and therefore re-opening the cryostat to move the arrays would occupy more than one week and we would have had no time for the second part of the re-commissioning (after the 2nd opening).
Participants
(preliminary)
On site: Angel, Stergios, Stefano, Carsten, Juan Macias-Perez (to be confirmed)
Remotely: Nicolas (except 18/3 @ 17 and 21/3 in the evening), Xavier (20-24/3), Samuel, Alessia (18-21/3)
Brisa is warned of the chance of using EMIR if anything goes wrong with NIKA2
Overall schedule
- March 4th - 11th: NIKA2 hardware upgrade
- March 11th - 17th: NIKA2 cooling down (maybe start already on the 9th, see above)
- March 18th: start the re-commissioning of NIKA2, after cooling down
We are going to use the use t22 account
-> copy the current scripts into the directory PaKo/202503/IMPORTANT NOTE: if problems pop up during the recommissioning?
-> re-open! (hardware people be ready)
-> use EMIR meanwhile- March 18: the first action is the new sweep (Martino, Alessandro, Dave)
- we then spend one-two days for the first characterization of the arrays, aimed at determining the new kidpars (IDL pipeline). Nicolas will work with us remotely during these first phase. Details are given below.
- this process will take ~2 days, including the new kidpars/DAFs and likely also the verification of the relative focus between the arrays. It might be faster, but let's count ~2 days
- at this stage we will know if we need/want to re-open the cryostat to adjust
the relative position of the arrays (along the z axis).
the re-opening will happen (very likely) and is already scheduled for March 30th (Sunday).
For the rest of the March 18-25th week, we proceed with the first part of the re-commissioning, aimed at characterizing the new arrays and test/characterize as much as possible the upgraded NIKA2
On March 25th (Tuesday, maintenance day) @ 10:30: start warming up NIKA2
On March 30th (Sunday) @ 10:30 the 2nd hardware intervention will begin and will take 2 days (until Tuesday morning). The arrays will be moved along the z-axis in order to bring them to the same focus (as much as possible)
The 2nd half of the re-commissioning (after the 2nd intervention) will be at the end of May or beginning of June, because April is fully taken by EHT and in the first half of May not everyone will be available.
we decide not to re-open (unlikely).
We proceed with as many re-commissioning operations as possible, including the full characterization of the instrument, as described in the next Section below, including stage-2 operations such as a pointing session and de-focused beam-maps.
Detailed operations
new sweep, closed window.
This will show already if any KID has enhanced noise.
(no info about the dichroic performance)check DAQ on sky, check traces: <<BR> we could again already see if there are problems with some KIDs<<BR> noise properties
also shows if the dichroic is healthy
check source and beam width
pointing, focus, pointing, beam-map
This very first observations might be a bit tricky, because we likely do not have the possibility to alternate the new sweep to the old sweep (because we have completely new arrays). Nicolas will intervene and use the IDL pipeline to determine the first kidpars.
We have new arrays, therefore:- first guess of kidpars from Martino's design
- a full beam map would take 30 min and the data red of a full beam map, take roughly the same time
- Therefore we decide to take a smaller beam map, on the central kids only
- check the source on the TOI, if it's here, then proceed
- process the small beam map
- if on focus, determine kidpars for central KIDs, otherwise refocus and repeat
- the smaller beam-map saves 1-2 hours over the whole procedure
the reference (central) pixel shall be determined!
- when on focus and the central kidpars are there, proceed
- full beam maps
- full kidpars
- produce also PIIC preliminary RPPs (Stefano)
- This might take up to ~2 days. Hopefully faster, but let's keep some margin.
- any possible idle times could be filled by EMIR or with the PIMP
- I insert the PIMP operations here, but they could be performed also later,
in case there's no occasion at this point:
Determine / check the passbands with the PIMP <<BR> Who on site is able to run the PIMP? <<BR> Samuel will be available online to instruct Stefano or others at the telescope on how to use it.
Moreover the online documentation will help (see the NIKA2 Wiki)
The PIMP needs a special .ini file for the DAQ
The PIMP will be craned up to the cabin in advance (either during the Holography week, or during the NIKA2 hardware intervention)
Analyse the PIMP data: Juan - Once the full beam maps and kidpars/DAFs will be ready and analysed, we will assess the "flat field", i.e. we assess if the current shadowing caused by the old dichroic is gone. We can also assess how big is the difference in beam shape/s (i.e. focus) across the f.o.v.
- with the focus maps + beam maps, we assess immediately how much is the focus difference between Arrays 1,2,3. few scans are in principle enough, but we'll need some statistics, in order to be more conclusive and determine the offset with high enough precision. These scans can be part of the initial 2 days, or might some more time, depending on how long it takes us to complete the kidpars/DAFs.
- At this point, we can asses the focus situation and meet a decision: does the upgraded NIKA2 need to be opened again, so to optimize the
(relative) position of the three arrays and bring them to the same focus?
Are there any other issues that need to be solved by opening the cryostat?
- we decide that we need/want to re-open the cryostat to adjust the relative position of the arrays and bring them to the same focus. [and/or to solve any other issues]
- assess by how much the arrays need to be moved (and which arrays) [Samuel, simulations vs. observations]
- the re-opening is already scheduled for March 30th, two days. Notify the hardware people that they need to prepare to come to the telescope.
- proceed with the re-commissioning for the remaining days, up to March 25th.
- keep taking pointing, focus, calib_1scan, beam maps of calibrators
beam maps of Uranus in total power AND polarimetry mode
Polarized beam maps of QSOs
Importantly, polarized beam maps of 3C286- perform the full characterization of the arrays and NEFD in total power. Preferred targets
1h on HLS (bright source)
older scans are available before any upgrade (telescope and NIKA2)
first assessment of new sensitivity
if good, then spend time on G2 (faint source)deep integration on faint source G2 (5-10 hours)
older scans are available before any upgrade (telescope and NIKA2)Orion-B big maps with extended emission
older scans are available before 30m painting and after painting (before NIKA upgrade)M8182 big maps with empty sky, a bright compact source and a faint extended source
older scans are available during new servo system upgrade, before 30m painting
perform the full characterization of NIKA2-Pol.
If the external calibrator is confirmed to be working properly, use it too!
Preferred targets:- polarimetry QSOs
- polarimetry Crab Nebula
- beam map on 3C286
- beam map Uranus in pol-mode
- If the external calibrator is confirmed to be working properly, take some scans with the external calibrator on and off. We need to characterize the zero level of the external calibrator. To this aim, short scans are sufficient.
- the NIKA2 warming up will start on March 25th @ 10:30
- the 2nd hardware intervention will happen from March 30th to April 1st
- the 2nd part of the re-commissioning will take place either during the last week of May or during the first week of June
we decide that we do not need/want to re-open the cryostat.
- proceed with the full re-commissioning on NIKA2 for the remaining days, up to March 25th.
- keep taking pointing, focus, calib_1scan, beam maps of calibrators
- perform a full pointing session
beam maps of Uranus in total power AND polarimetry mode
polarized beam maps of QSOs
importantly, polarized beam maps of 3C286
- take also de-focused beam maps (with few different focus positions; be aware that this takes quite some time). The aim is to determine the best offset to use in order to have the best focus on avg over the whole focal surface (at the moment this is the "famous" 0.2 mm offset).
perform the full characterization of the arrays and NEFD in total power.
Preferred targets:1h on HLS (bright source)
older scans are available before any upgrade (telescope and NIKA2)
first assessment of new sensitivity
if good, then spend time on G2 (faint source)deep integration on faint source G2 (5-10 hours)
older scans are available before any upgrade (telescope and NIKA2)Orion-B big maps with extended emission
older scans are available before 30m painting and after painting (before NIKA upgrade)M8182 big maps with empty sky, a bright compact source and a faint extended source
older scans are available during new servo system upgrade, before 30m painting
perform the full characterization of NIKA2-Pol.
If the external calibrator is confirmed to be working properly, use it too!
Preferred targets:- polarimetry QSOs
- polarimetry Crab Nebula
- beam map on 3C286
- beam map Uranus in pol-mode
- If the external calibrator is confirmed to be working properly, takes some scans with the external calibrator on and off We need to characterize the zero level of the external calibrator. To this aim, short scans are sufficient.
- the re-commissioning ends on March 25th
- if necessary, a 2nd re-commissioning week will happen either on the last week of May, or on the first week of June
- we decide that we need/want to re-open the cryostat to adjust the relative position of the arrays and bring them to the same focus. [and/or to solve any other issues]
Second part of the re-commissioning
Either in the case that the cryostat is opened a second time on march 30th, or it's not re-opened but this re-commissioning week is not enough to perform all needed observations, we will have a second part of the re-commissioning.
It will take place during the last week of May or during the first week of June. We can reserve only one week.
If this second chance is washed away by bad weather, we will shift to September