Differences between revisions 5 and 6
Revision 5 as of 2009-02-03 10:56:11
Size: 853
Editor: visitor3
Comment:
Revision 6 as of 2009-02-03 10:56:34
Size: 844
Editor: visitor3
Comment:
Deletions are marked like this. Additions are marked like this.
Line 4: Line 4:
| 11 | 10.3.-17.3. | ABCD Dismounting | | SN | | 
| | | Transport | | | |  
| 12 | 17.3.-24.3. | EMIR Installation | | SN/BL | | 
| 11 | 10.3.-17.3. | ABCD Dismounting | | SN | |
| | | Transport | | | |
| 12 | 17.3.-24.3. | EMIR Installation | | SN/BL | |
Line 8: Line 8:
| 14 | 31.3.-7.4. | EMIR Commissioning (Week #1) | | CT | | | | 
| 15 | 7.4.-14.4. | | | | | | |  
| 16 | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | | 
| 17 | 21.4.-28.4. | TBA | | | | | | 
| 14 | 31.3.-7.4. | EMIR Commissioning (Week #1) | | CT | | | |
| 15 | 7.4.-14.4. | | | | | | |
| 16 | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | |
| 17 | 21.4.-28.4. | TBA | | | | | |

EMIR Installation and Commissioning at the IRAM 30m telescope

| Week | Dates | Main Task | Details | Lead | People | | 11 | 10.3.-17.3. | ABCD Dismounting | | SN | | | | | Transport | | | | | 12 | 17.3.-24.3. | EMIR Installation | | SN/BL | | | 13 | 24.3.-31.3. | EMIR Hardware Testing & First Light | | SN/BL | | | 14 | 31.3.-7.4. | EMIR Commissioning (Week #1) | | CT | | | | | 15 | 7.4.-14.4. | | | | | | | | 16 | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | | | 17 | 21.4.-28.4. | TBA | | | | | |