Differences between revisions 15 and 25 (spanning 10 versions)
Revision 15 as of 2025-02-18 13:55:47
Size: 1494
Comment:
Revision 25 as of 2025-02-18 15:56:32
Size: 1983
Comment:
Deletions are marked like this. Additions are marked like this.
Line 14: Line 14:
15:00-22:00: Stergios: Basic training on NIKA2/EMIR observations. Wind gusts up to 20m/s thus we wait a couple of minutes for the weather to improve. 15:00-22:00: Stergios: Basic training on NIKA2/EMIR observations. 15:00 LT: Wind gusts up to 20m/s thus we wait a couple of minutes for the weather to improve. At 16:21 LT we started with tuning with EMIR to project 143-24. Spindle errors and homology at scan 18, 19, 20, 21 (good start...). Operator moves in elevation manually. Now the plots are not appearing but the imbfits are created. Problem located, apparently we don't get the plots with the project account 'test', so we will observe with project poolw-24 for now. Under the poolw-24 account we get the calibration plots but not the pointing ones. Trying with the 143-24 project.
Line 21: Line 21:
10:00-16:00: Marie-Anne: 10:00-16:00: Paul:
Line 23: Line 23:
16:00-22:00: Paul: 16:00-22:00: Marie-Anne:
Line 30: Line 30:
10:00-16:00: Marie-Anne: 10:00-16:00: Paul:
Line 32: Line 32:
16:00-22:00: Paul: 16:00-22:00: Marie-Anne:
Line 39: Line 39:
10:00-16:00: Marie-Anne: 10:00-16:00: Paul:
Line 41: Line 41:
16:00-22:00: Paul: 16:00-22:00: Marie-Anne:
Line 48: Line 48:
10:00-16:00: Marie-Anne: 10:00-16:00: Paul:
Line 50: Line 50:
16:00-22:00: Paul: 16:00-22:00: Marie-Anne:
Line 57: Line 57:
10:00-16:00: Marie-Anne: 10:00-16:00: Paul:
Line 59: Line 59:
16:00-22:00: Paul: 16:00-22:00: Marie-Anne:
Line 66: Line 66:
10:00-16:00: Marie-Anne: 10:00-16:00: Paul:
Line 68: Line 68:
16:00-22:00: Paul: 16:00-22:00: Marie-Anne:
Line 70: Line 70:
22:00-03:30: Carsten: 22:00-04:00: Carsten:

Back to the NIKA2 main page

Daily Reports

Observers on-site: Michael Mattern, Marie-Anne Carpine, Paul Law, Carsten Kramer and Stergios Amarantidis (AoD).

Operators: Gloria (day), Sergio (night).

All times are in Local Time.

Feb 18th, Tuesday

Maintenance: during maintenance CD tried to fix E1 (apparently the issue was found) and we conducted some tests with E0,1,2,3 (just tuning in some corresponding frequencies for each band).

15:00-22:00: Stergios: Basic training on NIKA2/EMIR observations. 15:00 LT: Wind gusts up to 20m/s thus we wait a couple of minutes for the weather to improve. At 16:21 LT we started with tuning with EMIR to project 143-24. Spindle errors and homology at scan 18, 19, 20, 21 (good start...). Operator moves in elevation manually. Now the plots are not appearing but the imbfits are created. Problem located, apparently we don't get the plots with the project account 'test', so we will observe with project poolw-24 for now. Under the poolw-24 account we get the calibration plots but not the pointing ones. Trying with the 143-24 project.

22:00-04:00: Carsten:

Feb 19th, Wednesday

04:00-10:00: Michael:

10:00-16:00: Paul:

16:00-22:00: Marie-Anne:

22:00-04:00: Carsten:

Feb 20th, Thursday

04:00-10:00: Michael:

10:00-16:00: Paul:

16:00-22:00: Marie-Anne:

22:00-04:00: Carsten:

Feb 21st, Friday

04:00-10:00: Michael:

10:00-16:00: Paul:

16:00-22:00: Marie-Anne:

22:00-04:00: Carsten:

Feb 22nd, Saturday

04:00-10:00: Michael:

10:00-16:00: Paul:

16:00-22:00: Marie-Anne:

22:00-04:00: Carsten:

Feb 23rd, Sunday

04:00-10:00: Michael:

10:00-16:00: Paul:

16:00-22:00: Marie-Anne:

22:00-04:00: Carsten:

Feb 24th, Monday

04:00-10:00: Michael:

10:00-16:00: Paul:

16:00-22:00: Marie-Anne:

22:00-04:00: Carsten:

Feb 25th, Tuesday

03:30-10:30: Project 169-24 (EMIR; XPOL):

DailyReportsNika2Pool180225 (last edited 2025-02-25 08:26:15 by NikaBolometer)