⇤ ← Revision 1 as of 2022-11-06 13:30:28
320
Comment:
|
943
|
Deletions are marked like this. | Additions are marked like this. |
Line 9: | Line 9: |
16:30 - 21:00; Ioannis & Alice: Maintenance finished at 16:30 but wind was too high to start with observations. Wind speed reduced a bit by 18:00 and started system check with EMIR because Tau225 was ~0.4-0.5 at that time and expected to increase further. Observations for EMIR backup project 056-22 between 19:00 and 21:00 for objects G053.23 and G49.48 until atmosphere became too unstable to continue (pwv fluctuations between 6mm and 10mm). 21:00 - 03:00; Hélène: Tried a couple of pointings but atmosphere was too unstable. Observations stopped at 21:50 due to high wind speed. |
|
Line 10: | Line 14: |
03:00 - 09:00; Philippe: ... |
Daily Reports
Contents
Nov 8th, Tuesday
16:30 - 21:00; Ioannis & Alice: Maintenance finished at 16:30 but wind was too high to start with observations. Wind speed reduced a bit by 18:00 and started system check with EMIR because Tau225 was ~0.4-0.5 at that time and expected to increase further. Observations for EMIR backup project 056-22 between 19:00 and 21:00 for objects G053.23 and G49.48 until atmosphere became too unstable to continue (pwv fluctuations between 6mm and 10mm).
21:00 - 03:00; Hélène: Tried a couple of pointings but atmosphere was too unstable. Observations stopped at 21:50 due to high wind speed.
Nov 9th, Wednesday
03:00 - 09:00; Philippe: ...
Nov 10th, Thursday
Nov 11th, Friday
Nov 12th, Saturday
Nov 13th, Sunday
Nov 14th, Monday