=== PreparationRun Sun 12/05 ===
Left Grenoble by car in the morning, stopped at Calp
[[PrepRun6|Go to preparation run daily reports]]
Line 6: Line 5:
=== PreparationRun Mon 13/05 ===
Arrived at the telescope around 3:30pm. Unloaded the car, installed archeops8, archeops9 and THz in the control room. Updated with SVN. Experiment file for next NIKA run: nika_iram2.txt
Preparation visit before Run6
Line 9: Line 7:
A few mbars of something in the cryostat (J1=50mbar). [[NikaRun6|Back to the NIKA run 6]]
Line 11: Line 9:
=== PreparationRun Tue 14/05 ===
GISMO electronics is still there. Thus first we'll have to wait that it's craned down before starting working on the cryostat. We re-pump the cryostat and the big pumping pipe before the intervention. Jpi is growing up a bit after pumping; 1e-3mbar per minute roughly. Not very dangerous, could be outgassing, but I have seen better. Could be a small leak at the O-rings. In any case we have to open later.


=== Daily Reports ===

=== Mon 03/06 ===
Left Grenoble by car in the morning. Andrea, Alain, Alessandro. Reached the telescope at 20h30.

=== Tue 04/06 ===
During the maintenance craned up again NIKA, installed. '''Warm impedance test: 20mbar/min at 3 bar'''

Start cooling down at 13h30.

Test with VNA at 300K:

{{attachment:VNA_1mm.jpg||width=600}}
{{attachment:VNA_2mm.jpg||width=600}}

''figures: VNA scans at 300K (0-8GHz). Left: 1mm array; right: 2mm array.''

Installed the electronics,

{{attachment:nika_back_1.jpg||width=600}}
{{attachment:NIKA_back_2.jpg||width=600}}

''figures: NIKA installed again''

Back to the NIKA run6 page

Go to preparation run daily reports

Preparation visit before Run6

Back to the NIKA run 6

Daily Reports

Mon 03/06

Left Grenoble by car in the morning. Andrea, Alain, Alessandro. Reached the telescope at 20h30.

Tue 04/06

During the maintenance craned up again NIKA, installed. Warm impedance test: 20mbar/min at 3 bar

Start cooling down at 13h30.

Test with VNA at 300K:

VNA_1mm.jpg VNA_2mm.jpg

figures: VNA scans at 300K (0-8GHz). Left: 1mm array; right: 2mm array.

Installed the electronics,

nika_back_1.jpg NIKA_back_2.jpg

figures: NIKA installed again