Back to the NIKA2 main page

To start polarimetric observations with NIKA2

1. Put rotating half-wave plate (HWP) in the optical path on NIKA2

2. Start the server for MPPSYNC, needed for the HWP operation

3. Restart the acquisition software (LAUNCH ACQUI_V3_IRAM) on the nika2-a machine with the correct ini file

4. Check the MPPSYNC value in the acquisition window

5. Start the resonances monitor (LAUNCH MON_V3_IRAM), as usual 6. Launch HWP operation window

7. Set the phase of the HWP

8. Start observations and real-tile data reduction. At the moment, the polarization data are reduced with the IDL pipeline

To go back to total power observations

1. Stop the HWP rotation and turn it off

2. Close the acquisition software as usual

3. Restart the acquisition software (LAUNCH ACQUI_V3_IRAM) on the nika2-a machine with the correct ini file

4. Start the resonances monitor (LAUNCH MON_V3_IRAM) and proceed with the tuning as usual