Tuesday 14-May-2013: 10h (during maintenance) Open cryostat, replace array at 2mm and the 1mm cold amplifier. Install the new DC cables for the amplifier. Install a new 4K magnetic screen. Install electronics rack in the cabin and connect. In the evening, start cooling down. | ==== Plan ==== Tuesday 14-May-2013: 10h (during maintenance) Open cryostat, replace array at 2mm and the 1mm cold amplifier. Install the new DC cables for the amplifier. Install a new 4K magnetic screen. Install electronics rack in the cabin and connect. Mount the anti-vibration legs on the pumping stage. In the evening, start cooling down. |
Line 11: | Line 13: |
18 May 2013: check resonances in a dark configuration and end the preparation as soon as it is ready | 18 May 2013: check resonances in a dark configuration and end the preparation as soon as it is ready. The cryostat stays cold until the observational run 6 in June. |
Line 14: | Line 16: |
==== Report ==== Tuesday 14-May-2013: All planned operation completed. Furthermore, mu-metal screening on 4K and 50K stages: - on 4K screen: (inner) METGLAS 2714A 2.0 inch x 0.6 mil std spec (bat), mu about 10000 @ 4K (outer) VITROVAC (same put on Sionludi @ Institu Néel) - on 50K screen: only METGLAS |
Preparation visit before Run6
In May 2013, 3 people come to the 30m to install the new 2mm array and replace the 1mm cold amplifier. Then, a cooling down will occur and the NIKA prototype stays cold until the Run6 proper starts.
Plan
Tuesday 14-May-2013: 10h (during maintenance) Open cryostat, replace array at 2mm and the 1mm cold amplifier. Install the new DC cables for the amplifier. Install a new 4K magnetic screen. Install electronics rack in the cabin and connect. Mount the anti-vibration legs on the pumping stage. In the evening, start cooling down.
15-17 May 2013: cooling down
18 May 2013: check resonances in a dark configuration and end the preparation as soon as it is ready. The cryostat stays cold until the observational run 6 in June.
Alessandro Monfardini, Martino Calvo and Nello D'Addabbo come by car from Grenoble.
Report
Tuesday 14-May-2013: All planned operation completed. Furthermore, mu-metal screening on 4K and 50K stages: - on 4K screen: (inner) METGLAS 2714A 2.0 inch x 0.6 mil std spec (bat), mu about 10000 @ 4K
- (outer) VITROVAC (same put on Sionludi @ Institu Néel)
- on 50K screen: only METGLAS