Line 49: Line 49:
The total number of rooms at the Pico is 14 => always full with above room distributions. The total number of rooms at the Pico is 14 => always full with above room atribution.

NIKA run #3 (18 - 24. Oct 2011)

Back to the NIKA main page

Test run plan:

Telescope Schedule

#

Dates

Main Task

Details

Lead (Neel / IRAM)

Support

11.10. Tuesday

Arrival of first visitors and truck in Granada

12.10. Wednesday

Mount and cool down

Limited access to Rx-Cabin: ~ 11h - 17h

Alain / Samuel

Santiago

13.10. Thursday

Cool down / Network / System checks

Limited access to Rx-Cabin: up to 2 hours in afternoon

Alain / Samuel

Miguel

14.10. Friday

Possible displacement of PTC compressor / cool, checks

Limited access to Rx-Cabin: up to 2 hours anytime

Alain / Samuel

Dave ? Santiago ?

15.10. Saturday

Possible displacement of PTC compressor / laser alignment

Limited access to Rx-Cabin: up to 2 hours anytime

Alain / Samuel

Dave ? Santiago ?

16.10. Sunday

cool down & checks or wait

access to Rx-Cabin: 0 - 2 hours, probably not necessary

Alain / Samuel

17.10. Monday

Observations (T21-11)

start at 22h00

Alain / Samuel

18.10. Tuesday

Observations (T21-11)

stop at 10h00, restart at 22h00

Alain / Samuel

19.10. Wednesday

Observations (T21-11)

stop at 14h00, restart at 22h00

Alain / Samuel

20.10. Thursday

Observations (T21-11)

stop at 14h00, restart at 22h00

Xavier, Alessandro / Samuel

21.10. Friday

Observations (T21-11)

stop at 14h00, restart at 22h00

Xavier, Alessandro / Samuel

22.10. Saturday

Observations (T21-11)

stop at 14h00, restart at 22h00

Xavier, Alessandro / Samuel

23.10. Sunday

Observations (T21-11)

stop at 14h00, restart at 20h00

Xavier, Alessandro / Samuel

24.10. Monday

Observations (T21-11), Warm up

stop at 14h00

Xavier, Alessandro / Samuel

25.10. Tuesday

Dismount and leave

Access to Rx-Cabin: 10h30 - 14h00

Xavier, Alessandro / Samuel

color table of the Run schedule

Staffing of the test run 3

  • IRAM/Grenoble:
    • 1 room: Samuel Leclercq (coordinator).
  • Institut Néel:
    • 3 rooms Oct 11 - Oct 18: Alain Benoit (PI) + (Christian Hoffmann), Alessandro Monfardini (co-PI) + Philippe Camus, Martino Calvo + (Angelo Cruciani).
    • 4 rooms Oct 18 - Oct 25: Alain Benoit (PI), Alessandro Monfardini (co-PI), Martino Calvo + Angelo Cruciani, Christian Hoffmann + Nicolas Boudou.
  • IPAG:
    • 1 room Oct 17 - Oct 25: François-Xavier Désert.
  • IRAM/Granada:
    • 2 rooms: Operators: Juan / Salvador.
    • 1 room: Astronomers of Duty: Sandra / Nicolas.
    • 2 rooms: cooks and cleaning personal.
    • 1 room: receiver engineer.
    • 2 rooms: several from various groups.
  • Visitors astronomers (heterodynes):
    • 2 rooms.

The total number of rooms at the Pico is 14 => always full with above room atribution.

For more details on traveling and presences dates see the color table of the NIKA staff schedule.

List of astronomical target

ListAstroTarget

Complementary information

Minutes of the September 9 2011 meeting for the preparation of the NIKA run 3

Test plan document as previous years probably not necessary since it would be redondant with all the above information (however if somebody thinks it would still be useful, please tell me and I'll write a test plan similar to previous years - Samuel).

Offline processing results

Daily reports