Differences between revisions 1 and 10 (spanning 9 versions)
Revision 1 as of 2011-09-14 10:19:56
Size: 705
Comment:
Revision 10 as of 2011-10-07 10:10:45
Size: 3949
Comment:
Deletions are marked like this. Additions are marked like this.
Line 8: Line 8:
|| '''#''' || '''Dates''' || '''Main Task''' || '''Details''' || '''Lead (IRAM / Neel)''' || '''Support''' ||
|| TO BE WRITTEN|| 13.10. || || Arrival of first visitors in Granada || || ||
|| '''#''' || '''Dates''' || '''Main Task''' || '''Details''' || '''Lead (Neel / IRAM)''' || '''Support''' ||
|| || 11.10. Tuesday || || Arrival of first visitors and truck in Granada || || ||
|| || 12.10. Wednesday || Mount and cool down || Limited access to Rx-Cabin: ~ 11h - 17h || Alain / Samuel || Santiago ||
|| || 13.10. Thursday || Cool down / Network / System checks || Limited access to Rx-Cabin: up to 2 hours in afternoon || Alain / Samuel || Miguel ||
|| || 14.10. Friday || Possible displacement of PTC compressor / cool, checks|| Limited access to Rx-Cabin: up to 2 hours anytime || Alain / Samuel || Dave ? Santiago ? ||
|| || 15.10. Saturday || Possible displacement of PTC compressor / laser alignment || Limited access to Rx-Cabin: up to 2 hours anytime || Alain / Samuel || Dave ? Santiago ? ||
|| || 16.10. Sunday || cool down & checks or wait || access to Rx-Cabin: 0 - 2 hours, probably not necessary || Alain / Samuel || ||
|| || 17.10. Monday || Observations ('''T21-11''') || start at 22h00 || Alain / Samuel || ||
|| || 18.10. Tuesday || Observations ('''T21-11''') || stop at 10h00, restart at 22h00 || Alain / Samuel || ||
|| || 19.10. Wednesday || Observations ('''T21-11''') || stop at 14h00, restart at 22h00 || Alain / Samuel || ||
|| || 20.10. Thursday || Observations ('''T21-11''') || stop at 14h00, restart at 22h00 || Xavier, Alessandro / Samuel || ||
|| || 21.10. Friday || Observations ('''T21-11''') || stop at 14h00, restart at 22h00 || Xavier, Alessandro / Samuel || ||
|| || 22.10. Saturday || Observations ('''T21-11''') || stop at 14h00, restart at 22h00 || Xavier, Alessandro / Samuel || ||
|| || 23.10. Sunday || Observations ('''T21-11''')|| stop at 14h00, restart at 20h00 || Xavier, Alessandro / Samuel || ||
|| || 24.10. Monday || Observations ('''T21-11'''), Warm up || stop at 14h00 || Xavier, Alessandro / Samuel || ||
|| || 25.10. Tuesday || Dismount and leave || Access to Rx-Cabin: 10h30 - 14h00 || Xavier, Alessandro / Samuel || ||
Line 11: Line 25:
== Staffing of the test run 3
== List of astronomical target (Final by FXD, 14.10.2010) ==
[[attachment:NikaRun3/Schedule_NIKArun3.pdf|color table of the Run schedule]]

== Staffing of the test run 3 ==

 * IRAM/Grenoble:
   * 1 room: Samuel Leclercq (coordinator).

 * Institut Néel:
   * 3 rooms Oct 11 - Oct 18: Alain Benoit (PI) + (Christian Hoffmann), Alessandro Monfardini (co-PI) + Philippe Camus, Martino Calvo + (Angelo Cruciani).
   * 4 rooms Oct 18 - Oct 25: Alain Benoit (PI), Alessandro Monfardini (co-PI), Martino Calvo + Angelo Cruciani, Christian Hoffmann + Nicolas Boudou.

 * IPAG:
   * 1 room Oct 17 - Oct 25: François-Xavier Désert.

 * IRAM/Granada:
   * 2 rooms: Operators: Juan / Salvador.
   * 1 room: Astronomers of Duty: Sandra / Nicolas.
   * 2 rooms: cooks and cleaning personal.
   * 1 room: receiver engineer.
   * 2 rooms: several from various groups.

 * Visitors astronomers (heterodynes):
   * 2 rooms.

The total number of rooms at the Pico is 14 => always full with above room atribution.

For more details on traveling and presences dates see the [[attachment:NikaRun3/Schedule_NIKA_visitors_Oct2011_.pdf|color table of the NIKA staff schedule]].

== List of astronomical target ==
Line 16: Line 57:
=== Complementary information ===

Minutes of the September 9 2011 meeting for the [[attachment:NikaRun3/Minutes_NIKA_prep_run_meeting_Sep_09_2011.pdf|preparation of the NIKA run 3]]

Test plan document as previous years probably not necessary since it would be redondant with all the above information (however if somebody thinks it would still be useful, please tell me and I'll write a test plan similar to previous years - Samuel).
Line 18: Line 65:
=== Above information plus more details (logistics, preparation of the run, sources list) on the following pdf document ===

NIKA run #3 (18 - 24. Oct 2011)

Back to the NIKA main page

Test run plan:

Telescope Schedule

#

Dates

Main Task

Details

Lead (Neel / IRAM)

Support

11.10. Tuesday

Arrival of first visitors and truck in Granada

12.10. Wednesday

Mount and cool down

Limited access to Rx-Cabin: ~ 11h - 17h

Alain / Samuel

Santiago

13.10. Thursday

Cool down / Network / System checks

Limited access to Rx-Cabin: up to 2 hours in afternoon

Alain / Samuel

Miguel

14.10. Friday

Possible displacement of PTC compressor / cool, checks

Limited access to Rx-Cabin: up to 2 hours anytime

Alain / Samuel

Dave ? Santiago ?

15.10. Saturday

Possible displacement of PTC compressor / laser alignment

Limited access to Rx-Cabin: up to 2 hours anytime

Alain / Samuel

Dave ? Santiago ?

16.10. Sunday

cool down & checks or wait

access to Rx-Cabin: 0 - 2 hours, probably not necessary

Alain / Samuel

17.10. Monday

Observations (T21-11)

start at 22h00

Alain / Samuel

18.10. Tuesday

Observations (T21-11)

stop at 10h00, restart at 22h00

Alain / Samuel

19.10. Wednesday

Observations (T21-11)

stop at 14h00, restart at 22h00

Alain / Samuel

20.10. Thursday

Observations (T21-11)

stop at 14h00, restart at 22h00

Xavier, Alessandro / Samuel

21.10. Friday

Observations (T21-11)

stop at 14h00, restart at 22h00

Xavier, Alessandro / Samuel

22.10. Saturday

Observations (T21-11)

stop at 14h00, restart at 22h00

Xavier, Alessandro / Samuel

23.10. Sunday

Observations (T21-11)

stop at 14h00, restart at 20h00

Xavier, Alessandro / Samuel

24.10. Monday

Observations (T21-11), Warm up

stop at 14h00

Xavier, Alessandro / Samuel

25.10. Tuesday

Dismount and leave

Access to Rx-Cabin: 10h30 - 14h00

Xavier, Alessandro / Samuel

color table of the Run schedule

Staffing of the test run 3

  • IRAM/Grenoble:
    • 1 room: Samuel Leclercq (coordinator).
  • Institut Néel:
    • 3 rooms Oct 11 - Oct 18: Alain Benoit (PI) + (Christian Hoffmann), Alessandro Monfardini (co-PI) + Philippe Camus, Martino Calvo + (Angelo Cruciani).
    • 4 rooms Oct 18 - Oct 25: Alain Benoit (PI), Alessandro Monfardini (co-PI), Martino Calvo + Angelo Cruciani, Christian Hoffmann + Nicolas Boudou.
  • IPAG:
    • 1 room Oct 17 - Oct 25: François-Xavier Désert.
  • IRAM/Granada:
    • 2 rooms: Operators: Juan / Salvador.
    • 1 room: Astronomers of Duty: Sandra / Nicolas.
    • 2 rooms: cooks and cleaning personal.
    • 1 room: receiver engineer.
    • 2 rooms: several from various groups.
  • Visitors astronomers (heterodynes):
    • 2 rooms.

The total number of rooms at the Pico is 14 => always full with above room atribution.

For more details on traveling and presences dates see the color table of the NIKA staff schedule.

List of astronomical target

ListAstroTarget

Complementary information

Minutes of the September 9 2011 meeting for the preparation of the NIKA run 3

Test plan document as previous years probably not necessary since it would be redondant with all the above information (however if somebody thinks it would still be useful, please tell me and I'll write a test plan similar to previous years - Samuel).

Offline processing results

Daily reports

NikaRun3 (last edited 2011-10-29 03:20:46 by 197)