Differences between revisions 27 and 29 (spanning 2 versions)
Revision 27 as of 2010-04-07 14:21:07
Size: 5959
Editor: GismoTeam
Comment:
Revision 29 as of 2010-04-07 14:35:03
Size: 5990
Editor: GismoTeam
Comment:
Deletions are marked like this. Additions are marked like this.
Line 37: Line 37:
 * 2 motorized neutral density filters allowing to compensate the restrained dynamic range of GISMO by reducing the optical transmission by 20% plus/or 50% in case of poor weather conditions.  * 2 motorized neutral density filters allowing to compensate the restrained dynamic range of GISMO by reducing the optical transmission in case of poor weather conditions, their transmissions are 65% and 40% respectively.

GISMO - The Goddard-IRAM Superconducting 2 Millimeter Observer

This page is maintained by CK, SL, and the GISMO team

3rd GISMO test run, April 2010

Staffing of the test run

  • GSFC: J. Staguhn, D. Fixsen, A. Kovacs, S. Maher, E. Sharp, D. Benford
  • IRAM: S. Leclercq, A. Sievers, G. Quintana-Lacaci, R. Zylka

Test run schedule: 31.03. - 16.04.2010

IRAM 30m schedule page: Schedule

T16-09 in 30m schedule = GISMO has telescope time

#

Dates

Main Task

Details

Lead (GSFC/IRAM)

Support

31.03. Wednesday

Arrival of ES, first GISMO visitor, in Granada

01.04.-05.04.

Mount upgrades, close and cool down in the 30m workshop

Arrival of SM

06.04. Tuesday

Turn on GISMO, and 1st tests in the 30m workshop

Arrival of JS, DF, AK, SL, AS.

Johannes / Samuel

Albrecht (AoD)

07.04.-08.04.

Tests in the 30m workshop

Bias, Tuning, IV curves, internal LED, Computer...

Johannes / Samuel

Albrecht (AoD)

09.04. Friday

Installation in the cabin, cool down, alignment, background noise

Arrival of RZ

Johannes / Samuel

Albrecht & Guillermo (AoD)

10.04.-12.04.

Calibration on sky (alignment, pointing, focus, dips), observations T16-09

12.04.: Arrival of DB, departure of AS, SL, RZ

Johannes / Samuel

Guillermo (AoD)

13.04.-15.04

Observations T16-09

Johannes

Guillermo (AoD)

16.04. Friday

Dismounting

Departure of everybody

Johannes

Guillermo (AoD)

GISMO upgrades compared to previous runs

  • 2 motorized neutral density filters allowing to compensate the restrained dynamic range of GISMO by reducing the optical transmission in case of poor weather conditions, their transmissions are 65% and 40% respectively.
  • A controllable shutter and a LED coupled to detectors through a fiber allowing to make optical internal calibration
  • Automated observing procedures usable via a dedicated GUI such as detector tunning, sky dips, I-V measurements for total power measurements
  • A reduction package (Crush) allowing near-to-real-time data processing
  • An observer's manual

Daily reports

31.03. - 05.04.

Arrival of Elmer & Stephen. Mount GISMO in the 30m workshop. The pictures below show several elements of the optical stage of GISMO: the 4K motors controlling the neutral density filters, the neutral density filters in motion, the baffle with the NDF motors and the 3He sorption cooler, and a general view of GISMO mounted.

  • GISMO_4K_NDfilters_motors.jpg GISMO_NDfilter_1_moves.jpg GISMO_NDfilter_2_moves.jpg GISMO_baffle_3He_cooler.jpg GISMO_mounted.jpg

Start cooling down on the 05.04.

06.04. & 07.04.

Arrival of Johannes, Dale, Attila, and Samuel. GISMO is cold. Turn on the instrument, BIAS the SQUIDs, monitor the TESs responses, take IV curves: all 4 quadrants are working, about ~20 non-responsive pixels (mostly due to SQUID issues in the MUX). LED illumination not visible in the real time data, but appears finely in reduced curves. Problems of strange wiggles in the IV curves. Install the GISMO frame in the cabin, but keep everything else (GISMO & electronics) in the workshop. Find next morning that the problem with the IV curves was surely due to a hard-drive misbehavior caused by a power supply failure. After replacement things looks fine, frequency plots show 1/f^2 noise certainly due to thermal oscillations. So far so good.


2nd GISMO Test run, October 2008

In October 2008, the GISMO team Johannes Staguhn, Stephen Maher, Elmer Sharp, Dale Fixsen, and Dominic Benford spent two weeks at the 30m observatory to first install their GISMO bolometer in the lab and then in the receiver cabin to test its performance on the sky. GISMO consists of 8x16 pixels with transition edge sensors (TES). The super conducting TES are read out by SQUID multiplexers. The nominal bandwidth is 125-175GHz, pixels are spaced by 14", the telescope HPBW is 17" at 2mm. Data are taken while the telescope is performing Lissajous scan patterns, without switching the secondary, to increase the mapping efficiency. An automated pipeline merges the GISMO data with the telescope data streams to create FITS files, being triggered by the IRAM messaging system. Data are then further reduced using the Goddard data reduction package.

The 2mm spectral range provides a unique terrestrial window enabling ground-based observations of the earliest active dusty galaxies in the universe and thereby allowing a better constraint on the star formation rate in these objects. Preliminary results from this second observing run at the 30m telescope look very promising.

(CK, 28-Oct-2008)

gismo-team.png
The GISMO team in the control room at the 30m telescope, after one week of 24 hours observing time. From left to right: Stephen Maher, Elmer Sharp, Johannes Staguhn, Dale Fixsen, Dominic Benford (Photo by A.Sievers on October, 27, 2008)


1st GISMO Test run, November 2007

GoddardIramSuperconductingTwoMillimeterCamera (last edited 2014-03-31 13:30:45 by gra-lx17)