Size: 1175
Comment:
|
Size: 1741
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 8: | Line 8: |
| * According to DJ, a new sweep is provided before the beginning of this re-commissioning week. We will proceed as usual: (i) point/focus with the old sweep, (ii) get beam maps with the new sweep, (iii) then observe with the old sweep until the new DAFs/Kidpars are ready (it usually takes few hours). | * According to DJ, a new sweep is provided before the beginning of this re-commissioning week. We will proceed as usual: (i) point/focus with the old sweep (run 91), (ii) get beam maps with the new sweep (run 92), (iii) then observe with the old sweep until the new DAFs/Kidpars are ready (it usually takes few hours). |
| Line 12: | Line 12: |
| * A complete report about the intervention of NIKA2+ for hardware adaptation to focus differences can be read [[https://publicwiki.iram.es/NIKA2%2BFocDiffAdaptWork|here]]. | * A complete report about the intervention of NIKA2+ for hardware adaptation to focus differences can be read [[https://publicwiki.iram.es/NIKA2%2BFocDiffAdaptWork|here]]. In principle, array 1 was not touched during the NIKA2+ intervention. Similar focus corrections are expected for all three arrays. |
| Line 16: | Line 16: |
| * For re-commissioning tests/observations, NIKA2 account t22 should be used. * If there is an opportunity to continue observations of the NIKA2 pool, or even heterodyne pool programs, use the nikaw-25 or poolw-25 accounts, respectively. |
|
| Line 18: | Line 22: |
| * New sweep (run 80) * produce high-quality DAFs/RPPs and Kidpars * determine the optimal Z focus position and study the focus surface * produce new final NEFDs for total power * produce new final NEFDs for polarimetry (probably and likely in Autumn). |
* New sweep (run 92) * Preliminary check of the system on sky, getting first pointing/focus corrections * Produce high-quality DAFs/RPPs and Kidpars * Determine the optimal Z focus position and study the new focus surface per array * Produce new final NEFDs, at least for total power (HLS091828 and HFLS3 were the most observed fields in the re-commissioning campaign of October 2025) == Observations priorities == |
Back to the NIKA2 Run 80 main page
Contents
Preliminaries (last update: 2026/03/17):
- According to DJ, a new sweep is provided before the beginning of this re-commissioning week. We will proceed as usual: (i) point/focus with the old sweep (run 91), (ii) get beam maps with the new sweep (run 92), (iii) then observe with the old sweep until the new DAFs/Kidpars are ready (it usually takes few hours).
- A correction of parameters P2 and P7 of the pointing model of NIKA2 is provided on Monday 23/3/2026 (based on the round mean of the most recent pointing corrections: ΔAz. = 4", ΔEl. = 6")
A complete report about the intervention of NIKA2+ for hardware adaptation to focus differences can be read here. In principle, array 1 was not touched during the NIKA2+ intervention. Similar focus corrections are expected for all three arrays.
Notes for the next (run 80) re-commissioning campaign (under construction):
- For re-commissioning tests/observations, NIKA2 account t22 should be used.
- If there is an opportunity to continue observations of the NIKA2 pool, or even heterodyne pool programs, use the nikaw-25 or poolw-25 accounts, respectively.
Main Goals
- New sweep (run 92)
- Preliminary check of the system on sky, getting first pointing/focus corrections
- Produce high-quality DAFs/RPPs and Kidpars
- Determine the optimal Z focus position and study the new focus surface per array
- Produce new final NEFDs, at least for total power (HLS091828 and HFLS3 were the most observed fields in the re-commissioning campaign of October 2025)