Differences between revisions 10 and 11
Revision 10 as of 2013-11-15 21:12:58
Size: 1752
Comment:
Revision 11 as of 2013-11-15 21:14:19
Size: 1762
Comment:
Deletions are marked like this. Additions are marked like this.
Line 31: Line 31:
 *Day-6 (Tu): Start cooling down (during mainteinance). Remotely with support in the cabin.  *Day-6 (Tu 14/1): Start cooling down (during mainteinance). Remotely with support in the cabin.
Line 33: Line 33:
 *Day1 (Tu): Intens; OTF_geometry Uranus. Pointing model.  *Day1 (Tu 21/1): Intens; OTF_geometry Uranus. Pointing model.

NIKA run #7 January 2014

Back to the NIKA run 7

Goals of the run

Test the final NIKA configuration on the sky with Winter conditions. Validate the pipeline. Test the polarization setup on the sky. 56h total. About 8h/day. Leave the cryostat cold and ready for the scientific run (#8) in February 2014.

  1. Characterization of the final NIKA prototype configuration (5h)
  2. Perform a new pointing model starting from the old NIKA Run6 one. (5h)
  3. Validate all sequences (pointing, focus, skydip, zigzag otf map, Lissajou map). (5h)
  4. Check the sensitivity and time estimator.(5h)
  5. Perform some science demonstration observations on a best effort basis: Check the noise integration for 6 hours oriented towards deep field measurements, Establish standard faint source photometry (6h mostly high-z faint sources (10-40 mJy).
  6. Perform on-sky measurements of polarization at 1 and 2 mm. Use planets, quasars, the Crab Nebula, CasA, and Orion. (24h).

Preparation of the run

TBW (Nov 2013)

Tentative schedule

  • 15-23h (Local time) on 21 and 22 January 2014 17-01h on 23, 24, 25, 26, et 27 January 2014

Real schedule

Real schedule

Program

  • Day-6 (Tu 14/1): Start cooling down (during mainteinance). Remotely with support in the cabin.
  • Days -2 (Sa), -1 (Su), 0 (Mo): KID tuning and technical tests.
  • Day1 (Tu 21/1): Intens; OTF_geometry Uranus. Pointing model.
  • Day2 (We): Polar; debug
  • Day3 (Th): Intens; Validate all sequences
  • Day4 (Fr): Polar; Planets, quasars
  • Day5 (Sa): Intens; Validate integration time
  • Day6 (Su): Polar; Crab Orion
  • Day7 (Mo): Backup