= NIKA run #7 Early 2014 = | = NIKA run #7 January 2014 = |
Line 7: | Line 7: |
Test the final NIKA configuration on the sky with Winter conditions. Validate the pipeline. Test the polarization setup on the sky. 75h total. About 10h/day. Leave the cryostat cold and ready for the scientific run (#8) in March 2014. | Test the final NIKA configuration on the sky with Winter conditions. Validate the pipeline. Test the polarization setup on the sky. 56h total. About 8h/day. Leave the cryostat cold and ready for the scientific run (#8) in February 2014. |
Line 10: | Line 10: |
2. Perform a new pointing model starting from the old NIKA Run6 one. (10h) | 2. Perform a new pointing model starting from the old NIKA Run6 one. (5h) |
Line 13: | Line 13: |
5. Perform some science demonstration observations on a best effort basis: TBD: Check the noise integration for 15 hours oriented towards deep field measurements, Establish standard faint source photometry (15h mostly high-z faint sources (10-40 mJy). 6. Perform on-sky measurements of polarization at 1 and 2 mm. Use quasars, the Crab Nebula, CasA, and some galactic extended sources. (20h). |
5. Perform some science demonstration observations on a best effort basis: Check the noise integration for 6 hours oriented towards deep field measurements, Establish standard faint source photometry (6h mostly high-z faint sources (10-40 mJy). 6. Perform on-sky measurements of polarization at 1 and 2 mm. Use planets, quasars, the Crab Nebula, CasA, and Orion. (24h). |
Line 20: | Line 20: |
Summary schedule of the run: TBW | == Tentative schedule == 15-23h (Local time) on 21 and 22 January 2014 17-01h on 23, 24, 25, 26, et 27 January 2014 Program: Day1: Intens; OTF_geometry Uranus. Pointing model. Day2: Polar; debug Day3: Intens; Validate all sequences Day4: Polar; Planets, quasars Day5: Intens; Validate integration time Day6: Polar; Crab Orion Day7: Backup |
NIKA run #7 January 2014
Goals of the run
Test the final NIKA configuration on the sky with Winter conditions. Validate the pipeline. Test the polarization setup on the sky. 56h total. About 8h/day. Leave the cryostat cold and ready for the scientific run (#8) in February 2014.
- Characterization of the final NIKA prototype configuration (5h)
- Perform a new pointing model starting from the old NIKA Run6 one. (5h)
- Validate all sequences (pointing, focus, skydip, zigzag otf map, Lissajou map). (5h)
- Check the sensitivity and time estimator.(5h)
- Perform some science demonstration observations on a best effort basis: Check the noise integration for 6 hours oriented towards deep field measurements, Establish standard faint source photometry (6h mostly high-z faint sources (10-40 mJy).
- Perform on-sky measurements of polarization at 1 and 2 mm. Use planets, quasars, the Crab Nebula, CasA, and Orion. (24h).
Preparation of the run
TBW (oct-nov 2013)
Tentative schedule
15-23h (Local time) on 21 and 22 January 2014 17-01h on 23, 24, 25, 26, et 27 January 2014
Program: Day1: Intens; OTF_geometry Uranus. Pointing model. Day2: Polar; debug Day3: Intens; Validate all sequences Day4: Polar; Planets, quasars Day5: Intens; Validate integration time Day6: Polar; Crab Orion Day7: Backup