NIKA run #6 (11-18 June 2013)

Back to the NIKA run 6

Goals of the run

Install and test the new 2mm array and the 1mm cold amplifier Then Commission the NIKA prototype. Full characterization of the system on sky, not an astronomical oriented run.

  1. Characterization of the final NIKA prototype configuration
  2. Commission all sequences (pointing, focus, skydip, zigzag otf map, Lissajou map).
  3. Test implementation of NIKA in NCS, and perform a complete calibration sequence including pointing model.
  4. Test quick pre-scan KID auto-tunings procedure.
  5. Test on site the new NIKEL electronics (that has been qualified in lab).
  6. Have a training session on how to start the NIKA cryogenics.
  7. Perform some science demonstration observations.

Preparation of the run

Telescope Schedule T21-13

Summary schedule of the run:

Dates

Main Event

09.11. Friday

Alessandro, Martino, Samuel at the 30m; start cooldown

13.11. Tuesday

Alessandro, Martino, Samuel, Nicolas P, Juan MP at the 30m; Start 7h/day telescope time period for testing, characterization, calibration

19.11. Monday

Teams overlapp, arrival Xavier, Andrea, A. Beleem

20.11. Tuesday

Departure 1st week team, start 16h/day telescope time observations

27.11. Tuesday

End of the run

Staff of the run

Phone contact: