GISMO run #7; 2nd pool run (November 2012)

Back to the GISMO main page

Staffing


Schedule: 05.04. - 21.04.2012

Summarized schedule of the run:

Dates

Main event

Friday 26/10 - Tuesday 30/10

Preparation: cool down, system checks, calibration

Tuesday 30/10 - Tuesday 13/11

Calibration (1st day); observing pool; Warm up & switch off (last day)


GISMO final version


Daily reports

Friday 26/10

We have the electronics and computers setup and GISMO is on the pump. IRAM left the electronics in the cabin which gave us a head start. We also decided to put the cabling above the floor (with a good metal cover) to reduce the chances of breaking thermometry cables while fishing cables and also to make setup/teardown easier. We also cleaned up the IRIG isolation cabling and put the isolator box in the rack. The server was a little stubborn to boot but eventually gave in. The server, client, crate, IRIG, are up and running. We also made some fresh clones of the server disk and tested the backup server (booted and started GISMO software). Created wire cover.

Saturday 27/10

Continuing without problem. Weather getting a little better. Continuing cooldown. Added nitrogen. Prepared GISMO Nexus for new run. Removed ground breaker from electronics circuit. Completed disk backups and setting up client. Elmer working on optical models and helium in-gassing prevention design.