GISMO run #6 (April 2012, 1st pool run)

Staffing

Schedule: 05.04. - 21.04.2012

IRAM 30m schedule page: http://www.iram.fr/IRAMFR/PV/sche/12/s15v1.html

Summarized schedule of the run:

Dates

Main event

Thursday 05/04 - Monday 09/04

Arrival of ES, SM and DF at the telescope with missing hardware, mount GISMO, cool down

Tuesday 10/04 - Tuesday 17/04

Arrival of JS, AK, SL, and AK at the telescope, alignment, calibration/characterization work (see test plan), pooled projects observations, departure DF, ES

Tuesday 17/04 - Tuesday 24/04

Departure SL AK, arrival DB AE, pooled projects observations

GISMO final version

Daily reports

Thursday 05/04 - Monday 09/04

ES, DF and IRAM staff mounted and cooled down GISMO at its final position (see pictures below). Everything looks fine, based temperature reached, nice response of the detectors, first light on Saturn shows a nice shape indicating the optics is fine.

Tuesday 10/04

JS, AK, AK, SL, AS at the telescope. Alignment with laser (SN anf DJ). Everything looks fine, but weather is bad.

Here's some pictures of GISMO installed in the 30m receiver cabin:

01_GISMO_installed_in_receiver_cabin.jpg 02_GISMO_with_M3_M4_M5_M6_mirrors.jpg 03_M3_M4_and_GISMO_electronics.jpg

Mid afternoon: abnormal temperature rise on the detector package. Maybe a little touch somewhere, vibrations transmission ... investigation underway. Weather 100% humid anyway.