Line 55: Line 55:

==== Saturday 10 March ====

Friday was a day off (e.i. without telescope time). Saturday (Friday-Saturday night) we worked hard all night long to understand our problem of excess power on the array. The summary of the results of our test and hypothesis about what's wrong with the present situation is the following:
1. When we mount GISMO at the telescope we see ~ 60K excess emission.
2. Our pupil is larger than it was in Samuel's Zemax models (miscommunication on the need for a smaller pupil). This causes an over-illumination of the primary.
3. However, the several cm over-illumination simulated in Zemax cannot not fully account for the observed ~60K excess. Therefore we kept searching for an explanation that would be consistent with the excess.
4. We had initially been suspicious about the optical properties of M5 (the new flat mirror). However Santiago told us that the mirror quality was certified by an independent company.
5. Tonight we looked again at M5 and it became very obvious that it has large scale deformations along one axis of the surface (see pictures and movies below). So we came to suspect that these deformations have to affect the illumination of the primary.
6. Samuel's Zemax simulations confirm that with the hypothesis that with a ratio of radius of curvature to size of the deformation that is equivalent to a half-pipe-shaped mirror with a 4.3 meters radius of curvature (see Zemax screen shots below), these large scale errors (we did not find a laser to measure those, will do when we have acess to the telescope again) the primary gets significantly over-illuminated, consistent with our predictions from the 60K excess.
7.We measured the pixel projections on the sky and obtain 10" pixel spacing in one direction and 19" spacing in the other (used to be 13.88" x 13.77" on sky last year). The 10" are consistent with Samuel's Zemacs calculations that use the estimated large scale structures on M5. Planets look quite crummy, even in the maps that use the measured pixel spacing on the sky.
8. However, we cannot yet account for the 19"in the other direction. A concave excess in one of the mirrors could account for it. We don't know which one this might be (M5?, M6?).
9. We hope we can find a way to replace M5 with a flat plate/mirror without errors. That is at the moment the only way to definitely confirm or rule-out our hypothesis that all the clues mentioned above seem to point out, and hopefully to resolve our observed image problems.

[[attachment:IMG_1256.jpg|{{attachment:08_M5_ripples_1.jpg}}]] [[attachment:IMG_1263.jpg|{{attachment:09_M5_ripples_2.jpg}}]] [[attachment:IMG_1264.jpg|{{attachment:10_M5_ripples_3.jpg}}]]

GISMO run #5 (March 2012): new optics and permanent position

Staffing of the test run

  • GSFC: J. Staguhn, D. Fixsen, A. Kovacs, S. Maher, E. Sharp,
  • IRAM: S. Leclercq, IRAM Granada staff

Test run schedule: 02.03. - 12.03.2012

IRAM 30m schedule page: http://www.iram.fr/IRAMFR/PV/sche/12/s09v1.html

GISMO does not appear with an explicit project number because the idea is to take up to 20 hours of the telescope time on the heterodyne pool (project 440-11). The decision for the time slots allocated to GISMO will be taken in real time (few to several hours in advance) through discussion between the GISMO team and the pool manager, based on observiong pool constraints (e.g. LST) and weather conditions.

Summarized schedule of the run:

Dates

Main event

Before 01.03.

Arrival of GISMO hardware at the telescope

02.03. Friday

Arrival of ES, SM and DF at the telescope, start mounting GISMO in the workshop

05.03. Monday

Arrival of JS, AK and SL at the telescope, GISMO cooled down

07.03. Wednesday - 11.03. Sunday

GISMO on sky slots (up to 20 hours total). DF takes plane on Fri 09.03.

More details on schedule, people, organization, hardware, and test plan: GISMO-On_Sky_Test_Plan_2012_v2.pdf

GISMO final version

  • Same 8x16 pixels as 2nd to 4th runs, working at 2mm (the –3dB window is 140-162 GHz), with an individual pixel size = 0.9 Fλ.

  • Same special features from previous runs: 2 motorized neutral density filters, controllable shutter, automated observing procedures usable via a dedicated GUI (see observer's manual), CRUSH reduction package.

  • New updates: cold baffle, final position in the receiver cabin with corresponding warm optics.

Daily reports

Friday 02 March - Sunday 05

Elmer, Steve and Dale arrived at the telescope, and start mounting GISMO, then cool it down.

Monday 05 March

Johannes and Samuel arrived at the telescope. GISMO was close to base temperature. Water on the entrance window of the big baffle. Blow boil off nitrogen to it, then just use a fan. Look at the sky through the open window. Nice IV curves even without neutral density filter ==> very good sign that there's much less stray light than last year, so sensitivity should improve...

01_GISMO_cold_in_workshop.jpg 02_GISMO_mirror_and_window_in_workshop.jpg

Tuesday 06 March

The installation of GISMO into the receiver cabin took most of the day and part of the night: check measurements and installation plan, built a crate, machine the shelve, etc., install the shelve first. Then in the afternoon move GISMO and all the other parts up in the cabin, and start mounting. Plug the electronics: few things to adjust but everything looks fine in the end. Some small offset in positions (less then 2.5cm) and orientation (less than a degree) of some of the elements. Simulate the effects of these offsets in Zemax: position offsets have almost no effect as long as the optical axis is well aligned (which we take care using the laser), angle offset very critical for the illumination of the pupil: we need a perfect alignment of the orientation of M6 toward M5; this will be done on the sky minimizing the load from the background (impossible to do it otherwise since a fraction of a degree is critical).

03_GISMO_shelve.jpg 04_GISMO_lifted.jpg 05_GISMO_on_crate_in_cabin.jpg 06_GISMO_installed_in_cabin.jpg 07_GISMO_electronics.jpg

Wednesday 07 March

We tried to get the correct radio alignment using sky, then a hot load around M5 edges, but were not successful. 3 problems: a touch of one of the M6 rods with the bottom of the shelve, SL mistake on which rotation should be applied to M6 to optimize pupil illumination. We dismounted M6 and got the bottom of the shelve machined. Gave back the telescope. Work on a better plan for alignment, and simulations: cold pupil a bit too big, some non negligible spillover on M1 may remain even at best alignment.

Tuesday 08 March

We mounted again M6, and used correct rotations to optimize illumination minimizing background on the sky. Time to fix some incompatible pako scripts with the current system (2 backends were define in the config script), we just had the time do take our first maps on Saturn (Mars too low) and derive first pointing parameters.

Saturday 10 March

Friday was a day off (e.i. without telescope time). Saturday (Friday-Saturday night) we worked hard all night long to understand our problem of excess power on the array. The summary of the results of our test and hypothesis about what's wrong with the present situation is the following: 1. When we mount GISMO at the telescope we see ~ 60K excess emission. 2. Our pupil is larger than it was in Samuel's Zemax models (miscommunication on the need for a smaller pupil). This causes an over-illumination of the primary. 3. However, the several cm over-illumination simulated in Zemax cannot not fully account for the observed ~60K excess. Therefore we kept searching for an explanation that would be consistent with the excess. 4. We had initially been suspicious about the optical properties of M5 (the new flat mirror). However Santiago told us that the mirror quality was certified by an independent company. 5. Tonight we looked again at M5 and it became very obvious that it has large scale deformations along one axis of the surface (see pictures and movies below). So we came to suspect that these deformations have to affect the illumination of the primary. 6. Samuel's Zemax simulations confirm that with the hypothesis that with a ratio of radius of curvature to size of the deformation that is equivalent to a half-pipe-shaped mirror with a 4.3 meters radius of curvature (see Zemax screen shots below), these large scale errors (we did not find a laser to measure those, will do when we have acess to the telescope again) the primary gets significantly over-illuminated, consistent with our predictions from the 60K excess. 7.We measured the pixel projections on the sky and obtain 10" pixel spacing in one direction and 19" spacing in the other (used to be 13.88" x 13.77" on sky last year). The 10" are consistent with Samuel's Zemacs calculations that use the estimated large scale structures on M5. Planets look quite crummy, even in the maps that use the measured pixel spacing on the sky. 8. However, we cannot yet account for the 19"in the other direction. A concave excess in one of the mirrors could account for it. We don't know which one this might be (M5?, M6?). 9. We hope we can find a way to replace M5 with a flat plate/mirror without errors. That is at the moment the only way to definitely confirm or rule-out our hypothesis that all the clues mentioned above seem to point out, and hopefully to resolve our observed image problems.

attachment:IMG_1256.jpg attachment:IMG_1263.jpg attachment:IMG_1264.jpg