[https://gra-lx1.iram.es/mainWiki/EmirProject EMIR] Installation and Commissioning at the IRAM 30m telescope

#

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

11

10.3.-17.3.

#1: ABCD Dismounting

Santiago

Dave, Gregorio, Pako

Transport

Truck

Jean-Yves

Helicopter

Javier

12

17.3.-24.3.

#2: Installation

Santiago/Bernard?

Jean-Yves?, Dave, Anne-Laure?

IF

Salvador, Gabriel

Software

Sebastien, Walter

Albrecht, Hans, Helmut

13

24.3.-31.3.

#3: First Light & Hardware Testing

Bernard?/Santiago

Anne-Laure?, Dave, Jean-Yves?

IF

Salvador, Gabriel

Software

Sebastien, Walter

Hans, Helmut

Astronomy

Albrecht

14

31.3.-7.4.

#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #1)

Clemens

Carsten

Software

Albrecht

Walter, Hans, Helmut

15

7.4.-14.4.

16

14.4.-21.4.

#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #2)

Carsten

Clemens

Software

Hans

Walter, Albrecht, Helmut

17

21.4.-28.4.

TBA

cf. also with

The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.