EMIR Installation and Commissioning at the IRAM 30m telescope
# |
Dates |
Main Task |
Details |
People at the 30m |
Standby in Granada |
|
|
|
|
|
Lead |
Staff |
Staff |
11 |
10.3.-17.3. |
ABCD Dismounting |
|
Santiago |
Dave, Gregorio, Pako |
|
|
|
Transport |
Truck |
Bernard |
|
|
|
|
|
Helicopter |
Javier |
|
|
12 |
17.3.-24.3. |
Installation |
|
Santiago & Bernard |
Dave |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software |
|
|
Walter, Albrecht, Hans, Helmut |
13 |
24.3.-31.3. |
Hardware Testing & First Light |
|
Santiago & Bernard |
Dave |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software |
|
|
Walter, Albrecht, Hans, Helmut |
14 |
31.3.-7.4. |
Commissioning (Week #1) |
|
Clemens |
Carsten |
|
|
|
|
Software |
|
|
Walter, Albrecht, Hans, Helmut |
15 |
7.4.-14.4. |
|
|
|
|
|
16 |
14.4.-21.4. |
Commissioning (Week #2) |
|
Carsten |
Clemens |
|
|
|
|
Software |
|
|
Walter, Albrecht, Hans, Helmut |
17 |
21.4.-28.4. |
TBA |
|
|
|
|