EMIR Installation and Commissioning at the IRAM 30m telescope

Week Dates Main Task Details Lead People
11 10.3.-17.3. ABCD Dismounting
Transport
12 17.3.-24.3. EMIR Installation
13 24.3.-31.3. EMIR Hardware Testing & First Light
14 31.3.-7.4. EMIR Commissioning (Week #1)
15 7.4.-14.4. Semana Santa
16 14.4.-21.4. EMIR Commissioning (Week #2)
17 21.4.-28.4. TBA