Timeline of Installation and Commissioning at the IRAM 30m telescope
the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here]
# |
Dates |
Main Task |
Details |
People at the 30m |
Standby in Granada |
|
|
|
|
|
Lead |
Staff |
Staff |
Installation Plan of SN: attachment:Plan001.pdf |
||||||
11 |
10.3.-17.3. |
#1: ABCD Dismounting |
|
Santiago |
|
|
|
|
Transport |
Truck/JYC:12.-15.3. |
|
|
|
|
|
|
Helicopter/16.3. |
Javier |
|
|
|
|
|
|
|
|
|
12 |
17.3.-24.3. |
#2: Installation |
|
Santiago |
Jean-Yves (16.-), Bruno (16.-), Dave |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software |
|
Sebastien (16.-), Walter |
Albrecht, Hans, Helmut |
|
|
|
|
|
|
|
13 |
24.3.-31.3. |
#3: First Light & Hardware Testing |
|
Santiago |
Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-27.3.)??? |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software / Astronomy |
|
Sebastien (-26.), Walter, Albrecht |
Hans, Helmut, Juan for the weekend |
|
|
|
Operator Training |
Manolo |
|
|
|
|
|
|
|
|
|
[https://gra-lx1.iram.es/mainWiki/EmirInstallationAndCommissioningPlan Commissioning Plan of CK] |
||||||
14 |
31.3.-7.4. |
#4: Commissioning |
|
Carsten |
Dirk Muders, Clemens |
|
|
|
|
Software / Astronomy |
|
Hans + TBC |
Walter, Hans, Helmut, Albrecht |
|
|
|
Operator Training |
Manolo |
|
|
|
|
|
|
|
|
|
15 |
7.4.-14.4. |
|
|
|
|
|
|
|
|
|
|
|
|
16 |
14.4.-21.4. |
#5: Commissioning |
|
Carsten |
Clemens, Albert |
|
|
|
|
Software / Astronomy |
|
Helmut + TBC |
Walter, Albrecht, Hans |
|
|
|
|
|
|
|
17 |
21.4.-28.4. |
TBA |
|
|
|
|
cf. also with
[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule],
[http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and
[http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.
Planets & Moon during Commissioning:
- Night time: Saturn (to 60deg elev)
- Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
- Full moon: 9.4.