|| 14 || 31.3.-7.4. || EMIR Commissioning (Week #1) || || CT || ||  || 14 || 31.3.-7.4. || EMIR Commissioning (Week #1) || || CT || ||

EMIR Installation and Commissioning at the IRAM 30m telescope

Week

Dates

Main Task

Details

Lead

People

11

10.3.-17.3.

ABCD Dismounting

SN

Transport

12

17.3.-24.3.

EMIR Installation

SN/BL

13

24.3.-31.3.

EMIR Hardware Testing & First Light

SN/BL

14

31.3.-7.4.

EMIR Commissioning (Week #1)

CT

15

7.4.-14.4.

16

14.4.-21.4.

EMIR Commissioning (Week #2)

CK

17

21.4.-28.4.

TBA