   Size: 3705 
  
  Comment:  
 | 
  
   Size: 3052 
  
  Comment:  
 | 
| Deletions are marked like this. | Additions are marked like this. | 
| Line 2: | Line 2: | 
|  * the EMIR homepage for IRAM staff is [[https://gra-lx1.iram.es/mainWiki/EmirProject|here]] || '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' || || || || || || '''Lead''' || '''Staff''' || '''Staff''' || ||||||||||||||<style="text-align: center;"> || || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || || || || || || Transport || Truck/JYC:12.-15.3. || || || || || || || || Helicopter/16.3. || Javier || || || || || || || || || || || || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago || Jean-Yves (16.-), Bruno (16.-), Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien (16.-), Walter || Albrecht, Hans, Helmut || || || || || || || || || || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing''' || || Santiago || Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-26.3.), Juan(23.,24.,27.3.-2.4.) || || || || || || IF || || || Salvador, Gabriel || || || || || Software / Astronomy || || Sebastien(-26.), Walter, Albrecht, Clemens(27.3.-) || Hans, Helmut || || || || || Operator Training || Manolo || || || || || || || || || || || ||||||||||||||<style="text-align: center;"> || || 14 || 31.3.-7.4. || '''#4: Commissioning''' || || Carsten || Dirk Muders, Sascha Trippe, Juan(27.3.-Thu), Denise(Fri-Mon) || || || || || || Software / Astronomy || || Hans, Clemens(-Fri), Helmut(Tue-Fri) || Walter, Albrecht, Gabriel || || || || || Operator Training || Manolo || || || || || || || || || || || || 15 || 7.4.-14.4. || 24 hours MAMBO2 pooled observations & Full Moon with EMIR || || || Breezy Ocana Flaquer(Mon-Tue) || || || || || || || || || || || 16 || 14.4.-21.4. || '''#5: Commissioning''' || || Carsten(Di-Mo) || Clemens(Di-Mo), Albert(Di-Mo), Melanie, Karl(Thu-Sun), Rebeca(Fri-Mon), Gabriel(Thu-Fri) || || || || || || Software / Astronomy || || || Helmut, Walter, Albrecht, Hans || || || || || || || || || || 17 || 21.4.-28.4. || '''#6: Commissioning & MAMBO Pool Observations''' || || Hans(EMIR), Denise(MAMBO), Albrecht(Mo-Di) || || Helmut, Gabriel ||  | 
|
| Line 3: | Line 31: | 
| * the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here] | cf. also with | 
| Line 5: | Line 33: | 
| || '''#''' || '''Dates'''       || '''Main Task'''        || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' || || || || || || '''Lead''' || '''Staff''' || '''Staff''' || || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || Dave, Gregorio, Paco, Salvador, Juan || || || || || IF-Cable exchange || || || || || || || || Installation of M5,M6,M7 || || || || || || || || Painting of receiver cabin || 13./14.3. || || || || || || || Transport || Truck/JYC:12.-15.3. || || || || || || || || Helicopter/16.3. || Javier || || || || || || || || || || || || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago || Jean-Yves, Bruno, Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut || || || || || || || || || || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Santiago || Jean-Yves, Anne-Laure(23.-31.), Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software / Astronomy || || Sebastien, Walter, Albrecht || Hans, Helmut || || || || || Operator Training || Manolo || || || || || || || || || || || || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Dirk Muders, Clemens || || || || || || Software / Astronomy || || Hans + TBC || Walter, Hans, Helmut, Albrecht || || || || || Operator Training || Manolo || || || || || || || || || || || || 15 || 7.4.-14.4. || || || || || || || || || || || || || || || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Clemens, Albert || || || || || || Software / Astronomy || || Helmut + TBC || Walter, Albrecht, Hans || || || || || || || || || || 17 || 21.4.-28.4. || TBA || || || || || cf. also with * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule], * [http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]  | 
 * [[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule|AoD Schedule]], * [[http://www.iram.es/IRAMES/groups/operator/opesched.htm|Operator Schedule]], and * [[http://www.iram.es/IRAMES/mainWiki/PoolW0809|schedule of MAMBO pooled observations]]  | 
| Line 42: | Line 39: | 
Timeline of Installation and Commissioning at the IRAM 30m telescope
the EMIR homepage for IRAM staff is here
#  | 
  Dates  | 
  Main Task  | 
  Details  | 
  People at the 30m  | 
  Standby in Granada  | 
|
  | 
  
  | 
  
  | 
  
  | 
  Lead  | 
  Staff  | 
  Staff  | 
  | 
||||||
11  | 
  10.3.-17.3.  | 
  #1: ABCD Dismounting  | 
  
  | 
  Santiago  | 
  
  | 
  
  | 
  | 
  
  | 
  Transport  | 
  Truck/JYC:12.-15.3.  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  Helicopter/16.3.  | 
  Javier  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
12  | 
  17.3.-24.3.  | 
  #2: Installation  | 
  
  | 
  Santiago  | 
  Jean-Yves (16.-), Bruno (16.-), Dave  | 
  
  | 
  | 
  
  | 
  
  | 
  IF  | 
  
  | 
  
  | 
  Salvador, Gabriel  | 
  | 
  
  | 
  
  | 
  Software  | 
  
  | 
  Sebastien (16.-), Walter  | 
  Albrecht, Hans, Helmut  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
13  | 
  24.3.-31.3.  | 
  #3: First Light & Hardware Testing  | 
  
  | 
  Santiago  | 
  Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-26.3.), Juan(23.,24.,27.3.-2.4.)  | 
  
  | 
  | 
  
  | 
  
  | 
  IF  | 
  
  | 
  
  | 
  Salvador, Gabriel  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  Sebastien(-26.), Walter, Albrecht, Clemens(27.3.-)  | 
  Hans, Helmut  | 
  | 
  
  | 
  
  | 
  Operator Training  | 
  Manolo  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  | 
||||||
14  | 
  31.3.-7.4.  | 
  #4: Commissioning  | 
  
  | 
  Carsten  | 
  Dirk Muders, Sascha Trippe, Juan(27.3.-Thu), Denise(Fri-Mon)  | 
  
  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  Hans, Clemens(-Fri), Helmut(Tue-Fri)  | 
  Walter, Albrecht, Gabriel  | 
  | 
  
  | 
  
  | 
  Operator Training  | 
  Manolo  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
15  | 
  7.4.-14.4.  | 
  24 hours MAMBO2 pooled observations & Full Moon with EMIR  | 
  
  | 
  
  | 
  Breezy Ocana Flaquer(Mon-Tue)  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
16  | 
  14.4.-21.4.  | 
  #5: Commissioning  | 
  
  | 
  Carsten(Di-Mo)  | 
  Clemens(Di-Mo), Albert(Di-Mo), Melanie, Karl(Thu-Sun), Rebeca(Fri-Mon), Gabriel(Thu-Fri)  | 
  
  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  
  | 
  Helmut, Walter, Albrecht, Hans  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
17  | 
  21.4.-28.4.  | 
  #6: Commissioning & MAMBO Pool Observations  | 
  
  | 
  Hans(EMIR), Denise(MAMBO), Albrecht(Mo-Di)  | 
  
  | 
  Helmut, Gabriel  | 
cf. also with
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.
Planets & Moon during Commissioning:
- Night time: Saturn (to 60deg elev)
 - Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
 - Full moon: 9.4.
 