| Size: 3482 Comment:  | Size: 3528 Comment:  | 
| Deletions are marked like this. | Additions are marked like this. | 
| Line 7: | Line 7: | 
| || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || Dave, Gregorio, Pako || || | |||||||||||||| '''Installation Plan of SN:''' attachment:Plan001.pdf || || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || || || | 
| Line 9: | Line 10: | 
| || || || || Helicopter/JL:16.3. || || || || | || || || || Helicopter/16.3. || Javier || || || | 
| Line 20: | Line 21: | 
| || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Dirk Muders, Clemens || || | |||||||||||||| '''[https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning Plan of CK]''' || || 14 || 31.3.-7.4. || '''#4: Commissioning''' || || Carsten || Dirk Muders, Clemens || || | 
| Line 26: | Line 28: | 
| || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Clemens, Albert?? || || | || 16 || 14.4.-21.4. || '''#5: Commissioning''' || || Carsten || Clemens, Albert || || | 
Timeline of Installation and Commissioning at the IRAM 30m telescope
- the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here] 
| # | Dates | Main Task | Details | People at the 30m | Standby in Granada | |
| 
 | 
 | 
 | 
 | Lead | Staff | Staff | 
| Installation Plan of SN: attachment:Plan001.pdf | ||||||
| 11 | 10.3.-17.3. | #1: ABCD Dismounting | 
 | Santiago | 
 | 
 | 
| 
 | 
 | Transport | Truck/JYC:12.-15.3. | 
 | 
 | 
 | 
| 
 | 
 | 
 | Helicopter/16.3. | Javier | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 12 | 17.3.-24.3. | #2: Installation | 
 | Santiago | Jean-Yves, Bruno, Dave | 
 | 
| 
 | 
 | 
 | IF | 
 | 
 | Salvador, Gabriel | 
| 
 | 
 | 
 | Software | 
 | Sebastien, Walter | Albrecht, Hans, Helmut | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 13 | 24.3.-31.3. | #3: First Light & Hardware Testing | 
 | Santiago | Jean-Yves, Anne-Laure(23.-31.), Dave | 
 | 
| 
 | 
 | 
 | IF | 
 | 
 | Salvador, Gabriel | 
| 
 | 
 | 
 | Software / Astronomy | 
 | Sebastien, Walter, Albrecht | Hans, Helmut | 
| 
 | 
 | 
 | Operator Training | Manolo | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning Plan of CK] | ||||||
| 14 | 31.3.-7.4. | #4: Commissioning | 
 | Carsten | Dirk Muders, Clemens | 
 | 
| 
 | 
 | 
 | Software / Astronomy | 
 | Hans + TBC | Walter, Hans, Helmut, Albrecht | 
| 
 | 
 | 
 | Operator Training | Manolo | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 15 | 7.4.-14.4. | 
 | 
 | 
 | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 16 | 14.4.-21.4. | #5: Commissioning | 
 | Carsten | Clemens, Albert | 
 | 
| 
 | 
 | 
 | Software / Astronomy | 
 | Helmut + TBC | Walter, Albrecht, Hans | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 17 | 21.4.-28.4. | TBA | 
 | 
 | 
 | 
 | 
cf. also with
- [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule], 
- [http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and 
- [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations] 
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.
Planets & Moon during Commissioning:
- Night time: Saturn (to 60deg elev)
- Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
- Full moon: 9.4.