   Size: 3472 
  
  Comment:  
 | 
  
   Size: 3528 
  
  Comment:  
 | 
| Deletions are marked like this. | Additions are marked like this. | 
| Line 7: | Line 7: | 
| || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || Dave, Gregorio, Pako || || | |||||||||||||| '''Installation Plan of SN:''' attachment:Plan001.pdf || || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || || ||  | 
| Line 9: | Line 10: | 
| || || || || Helicopter/JL:16.3. || || || || | || || || || Helicopter/16.3. || Javier || || || | 
| Line 15: | Line 16: | 
| || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Santiago || Jean-Yves, Anne-Laure (23.-31.), Dave, Jean-Yves? || || | || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Santiago || Jean-Yves, Anne-Laure(23.-31.), Dave || || | 
| Line 20: | Line 21: | 
| || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Clemens || Carsten || || | |||||||||||||| '''[https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning Plan of CK]''' || || 14 || 31.3.-7.4. || '''#4: Commissioning''' || || Carsten || Dirk Muders, Clemens || ||  | 
| Line 26: | Line 28: | 
| || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Clemens || || | || 16 || 14.4.-21.4. || '''#5: Commissioning''' || || Carsten || Clemens, Albert || || | 
Timeline of Installation and Commissioning at the IRAM 30m telescope
the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here]
#  | 
  Dates  | 
  Main Task  | 
  Details  | 
  People at the 30m  | 
  Standby in Granada  | 
|
  | 
  
  | 
  
  | 
  
  | 
  Lead  | 
  Staff  | 
  Staff  | 
Installation Plan of SN: attachment:Plan001.pdf  | 
||||||
11  | 
  10.3.-17.3.  | 
  #1: ABCD Dismounting  | 
  
  | 
  Santiago  | 
  
  | 
  
  | 
  | 
  
  | 
  Transport  | 
  Truck/JYC:12.-15.3.  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  Helicopter/16.3.  | 
  Javier  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
12  | 
  17.3.-24.3.  | 
  #2: Installation  | 
  
  | 
  Santiago  | 
  Jean-Yves, Bruno, Dave  | 
  
  | 
  | 
  
  | 
  
  | 
  IF  | 
  
  | 
  
  | 
  Salvador, Gabriel  | 
  | 
  
  | 
  
  | 
  Software  | 
  
  | 
  Sebastien, Walter  | 
  Albrecht, Hans, Helmut  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
13  | 
  24.3.-31.3.  | 
  #3: First Light & Hardware Testing  | 
  
  | 
  Santiago  | 
  Jean-Yves, Anne-Laure(23.-31.), Dave  | 
  
  | 
  | 
  
  | 
  
  | 
  IF  | 
  
  | 
  
  | 
  Salvador, Gabriel  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  Sebastien, Walter, Albrecht  | 
  Hans, Helmut  | 
  | 
  
  | 
  
  | 
  Operator Training  | 
  Manolo  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
[https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning Plan of CK]  | 
||||||
14  | 
  31.3.-7.4.  | 
  #4: Commissioning  | 
  
  | 
  Carsten  | 
  Dirk Muders, Clemens  | 
  
  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  Hans + TBC  | 
  Walter, Hans, Helmut, Albrecht  | 
  | 
  
  | 
  
  | 
  Operator Training  | 
  Manolo  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
15  | 
  7.4.-14.4.  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
16  | 
  14.4.-21.4.  | 
  #5: Commissioning  | 
  
  | 
  Carsten  | 
  Clemens, Albert  | 
  
  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  Helmut + TBC  | 
  Walter, Albrecht, Hans  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
17  | 
  21.4.-28.4.  | 
  TBA  | 
  
  | 
  
  | 
  
  | 
  
  | 
cf. also with
[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule],
[http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and
[http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.
Planets & Moon during Commissioning:
- Night time: Saturn (to 60deg elev)
 - Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
 - Full moon: 9.4.
 