| Size: 3455 Comment:  | Size: 3705 Comment:  | 
| Deletions are marked like this. | Additions are marked like this. | 
| Line 7: | Line 7: | 
| || 11   || 10.3.-17.3. || '''#1: ABCD Dismounting''' ||            || Santiago   || Dave, Gregorio, Pako || || || || || Transport || Truck || Jean-Yves || || || || || || || Helicopter || Javier || || || | || 11   || 10.3.-17.3. || '''#1: ABCD Dismounting''' ||            || Santiago   || Dave, Gregorio, Paco, Salvador, Juan || || || || || IF-Cable exchange || || || || || || || || Installation of M5,M6,M7 || || || || || || || || Painting of receiver cabin || 13./14.3. || || || || || || || Transport || Truck/JYC:12.-15.3. || || || || || || || || Helicopter/16.3. || Javier || || || | 
| Line 11: | Line 14: | 
| || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago/Bernard? || Jean-Yves?, Dave, Anne-Laure? || || | || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago || Jean-Yves, Bruno, Dave || || | 
| Line 15: | Line 18: | 
| || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Bernard?/Santiago || Anne-Laure?, Dave, Jean-Yves? || || | || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Santiago || Jean-Yves, Anne-Laure(23.-31.), Dave || || | 
| Line 20: | Line 23: | 
| || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Clemens || Carsten || || | || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Dirk Muders, Clemens || || | 
| Line 26: | Line 29: | 
| || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Clemens || || | || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Clemens, Albert || || | 
| Line 38: | Line 41: | 
| Planets & Moon: | Planets & Moon during Commissioning: | 
Timeline of Installation and Commissioning at the IRAM 30m telescope
- the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here] 
| # | Dates | Main Task | Details | People at the 30m | Standby in Granada | |
| 
 | 
 | 
 | 
 | Lead | Staff | Staff | 
| 11 | 10.3.-17.3. | #1: ABCD Dismounting | 
 | Santiago | Dave, Gregorio, Paco, Salvador, Juan | 
 | 
| 
 | 
 | IF-Cable exchange | 
 | 
 | 
 | 
 | 
| 
 | 
 | Installation of M5,M6,M7 | 
 | 
 | 
 | 
 | 
| 
 | 
 | Painting of receiver cabin | 13./14.3. | 
 | 
 | 
 | 
| 
 | 
 | Transport | Truck/JYC:12.-15.3. | 
 | 
 | 
 | 
| 
 | 
 | 
 | Helicopter/16.3. | Javier | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 12 | 17.3.-24.3. | #2: Installation | 
 | Santiago | Jean-Yves, Bruno, Dave | 
 | 
| 
 | 
 | 
 | IF | 
 | 
 | Salvador, Gabriel | 
| 
 | 
 | 
 | Software | 
 | Sebastien, Walter | Albrecht, Hans, Helmut | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 13 | 24.3.-31.3. | #3: First Light & Hardware Testing | 
 | Santiago | Jean-Yves, Anne-Laure(23.-31.), Dave | 
 | 
| 
 | 
 | 
 | IF | 
 | 
 | Salvador, Gabriel | 
| 
 | 
 | 
 | Software / Astronomy | 
 | Sebastien, Walter, Albrecht | Hans, Helmut | 
| 
 | 
 | 
 | Operator Training | Manolo | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 14 | 31.3.-7.4. | #4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] | 
 | Carsten | Dirk Muders, Clemens | 
 | 
| 
 | 
 | 
 | Software / Astronomy | 
 | Hans + TBC | Walter, Hans, Helmut, Albrecht | 
| 
 | 
 | 
 | Operator Training | Manolo | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 15 | 7.4.-14.4. | 
 | 
 | 
 | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 16 | 14.4.-21.4. | #5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] | 
 | Carsten | Clemens, Albert | 
 | 
| 
 | 
 | 
 | Software / Astronomy | 
 | Helmut + TBC | Walter, Albrecht, Hans | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 17 | 21.4.-28.4. | TBA | 
 | 
 | 
 | 
 | 
cf. also with
- [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule], 
- [http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and 
- [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations] 
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.
Planets & Moon during Commissioning:
- Night time: Saturn (to 60deg elev)
- Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
- Full moon: 9.4.