| [https://gra-lx1.iram.es/mainWiki/EmirProject EMIR] Installation and Commissioning at the IRAM 30m telescope | === Timeline of Installation and Commissioning at the IRAM 30m telescope === * the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here]  | 
| Line 5: | Line 7: | 
| || 11   || 10.3.-17.3. || '''#1: ABCD Dismounting''' ||            || Santiago   || Dave, Gregorio, Pako || || || || || Transport || Truck || Jean-Yves || || || || || || || Helicopter || Javier || || ||  | 
|| 11   || 10.3.-17.3. || '''#1: ABCD Dismounting''' ||            || Santiago   || Dave, Gregorio, Paco, Salvador, Juan || || || || || IF-Cable exchange || || || || || || || || Installation of M5,M6,M7 || || || || || || || || Painting of receiver cabin || 13./14.3. || || || || || || || Transport || Truck/JYC:12.-15.3. || || || || || || || || Helicopter/JL:16.3. || || || ||  | 
| Line 9: | Line 14: | 
| || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago/Bernard? || Jean-Yves?, Dave, Anne-Laure? || || | || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago || Jean-Yves, Bruno, Dave || || | 
| Line 13: | Line 18: | 
| || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Bernard?/Santiago || Anne-Laure?, Dave, Jean-Yves? || || | || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Santiago || Jean-Yves, Anne-Laure(23.-31.), Dave || || | 
| Line 18: | Line 23: | 
| || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Clemens || Carsten || || | || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Dirk Muders, Clemens || || | 
| Line 24: | Line 29: | 
| || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Clemens || || | || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Clemens, Albert || || | 
| Line 35: | Line 40: | 
Planets & Moon during Commissioning: * Night time: Saturn (to 60deg elev) * Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter * Full moon: 9.4.  | 
Timeline of Installation and Commissioning at the IRAM 30m telescope
the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here]
#  | 
  Dates  | 
  Main Task  | 
  Details  | 
  People at the 30m  | 
  Standby in Granada  | 
|
  | 
  
  | 
  
  | 
  
  | 
  Lead  | 
  Staff  | 
  Staff  | 
11  | 
  10.3.-17.3.  | 
  #1: ABCD Dismounting  | 
  
  | 
  Santiago  | 
  Dave, Gregorio, Paco, Salvador, Juan  | 
  
  | 
  | 
  
  | 
  IF-Cable exchange  | 
  
  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  Installation of M5,M6,M7  | 
  
  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  Painting of receiver cabin  | 
  13./14.3.  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  Transport  | 
  Truck/JYC:12.-15.3.  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  Helicopter/JL:16.3.  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
12  | 
  17.3.-24.3.  | 
  #2: Installation  | 
  
  | 
  Santiago  | 
  Jean-Yves, Bruno, Dave  | 
  
  | 
  | 
  
  | 
  
  | 
  IF  | 
  
  | 
  
  | 
  Salvador, Gabriel  | 
  | 
  
  | 
  
  | 
  Software  | 
  
  | 
  Sebastien, Walter  | 
  Albrecht, Hans, Helmut  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
13  | 
  24.3.-31.3.  | 
  #3: First Light & Hardware Testing  | 
  
  | 
  Santiago  | 
  Jean-Yves, Anne-Laure(23.-31.), Dave  | 
  
  | 
  | 
  
  | 
  
  | 
  IF  | 
  
  | 
  
  | 
  Salvador, Gabriel  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  Sebastien, Walter, Albrecht  | 
  Hans, Helmut  | 
  | 
  
  | 
  
  | 
  Operator Training  | 
  Manolo  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
14  | 
  31.3.-7.4.  | 
  #4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]  | 
  
  | 
  Carsten  | 
  Dirk Muders, Clemens  | 
  
  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  Hans + TBC  | 
  Walter, Hans, Helmut, Albrecht  | 
  | 
  
  | 
  
  | 
  Operator Training  | 
  Manolo  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
15  | 
  7.4.-14.4.  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
16  | 
  14.4.-21.4.  | 
  #5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]  | 
  
  | 
  Carsten  | 
  Clemens, Albert  | 
  
  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  Helmut + TBC  | 
  Walter, Albrecht, Hans  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
17  | 
  21.4.-28.4.  | 
  TBA  | 
  
  | 
  
  | 
  
  | 
  
  | 
cf. also with
[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule],
[http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and
[http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.
Planets & Moon during Commissioning:
- Night time: Saturn (to 60deg elev)
 - Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
 - Full moon: 9.4.
 