| Week | Dates | Main Task | Details | Lead | People |
| 11 | 10.3.-17.3. | ABCD Dismounting | | SN | |
| | | Transport | | | |
| 12 | 17.3.-24.3. | EMIR Installation | | SN/BL | |
| 13 | 24.3.-31.3. | EMIR Hardware Testing & First Light | | SN/BL | |
| 14 | 31.3.-7.4. | EMIR Commissioning (Week #1) | | CT | | | |
| 15 | 7.4.-14.4. | | | | | | |
| 16 | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | |
| 17 | 21.4.-28.4. | TBA | | | | | |
|| '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' ||
|| || || || || '''Lead''' || '''Staff''' || '''Staff''' ||
|| 11 || 10.3.-17.3. || ABCD Dismounting || || Santiago || Dave, Gregorio, Pako || ||
|| || || Transport || Truck || Bernard || || ||
|| || || || Helicopter || Javier || || ||
|| 12 || 17.3.-24.3. || Installation || || Santiago & Bernard || Dave || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 13 || 24.3.-31.3. || Hardware Testing & First Light || || Santiago & Bernard || Dave || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 14 || 31.3.-7.4. || Commissioning (Week #1) || || Clemens || Carsten || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 15 || 7.4.-14.4. || || || || || ||
|| 16 || 14.4.-21.4. || Commissioning (Week #2) || || Carsten || Clemens || ||
|| || || || Software || || || Walter, Albrecht, Hans, Helmut ||
|| 17 || 21.4.-28.4. || TBA || || || || ||

EMIR Installation and Commissioning at the IRAM 30m telescope

#

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

11

10.3.-17.3.

ABCD Dismounting

Santiago

Dave, Gregorio, Pako

Transport

Truck

Bernard

Helicopter

Javier

12

17.3.-24.3.

Installation

Santiago & Bernard

Dave

Software

Walter, Albrecht, Hans, Helmut

13

24.3.-31.3.

Hardware Testing & First Light

Santiago & Bernard

Dave

Software

Walter, Albrecht, Hans, Helmut

14

31.3.-7.4.

Commissioning (Week #1)

Clemens

Carsten

Software

Walter, Albrecht, Hans, Helmut

15

7.4.-14.4.

16

14.4.-21.4.

Commissioning (Week #2)

Carsten

Clemens

Software

Walter, Albrecht, Hans, Helmut

17

21.4.-28.4.

TBA

cf. also with