| | Week | Dates | Main Task | Details | Lead | People | | 11 | 10.3.-17.3. | ABCD Dismounting | | SN | | | | | Transport | | | | | 12 | 17.3.-24.3. | EMIR Installation | | SN/BL | | | 13 | 24.3.-31.3. | EMIR Hardware Testing & First Light | | SN/BL | | | 14 | 31.3.-7.4. | EMIR Commissioning (Week #1) | | CT | | | | | 15 | 7.4.-14.4. | | | | | | | | 16 | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | | | 17 | 21.4.-28.4. | TBA | | | | | | |
|| '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' || || || || || || '''Lead''' || '''Staff''' || '''Staff''' || || 11 || 10.3.-17.3. || ABCD Dismounting || || Santiago || Dave, Gregorio, Pako || || || || || Transport || Truck || Bernard || || || || || || || Helicopter || Javier || || || || 12 || 17.3.-24.3. || Installation || || Santiago & Bernard || Dave || || || || || || Software || || || Walter, Albrecht, Hans, Helmut || || 13 || 24.3.-31.3. || Hardware Testing & First Light || || Santiago & Bernard || Dave || || || || || || Software || || || Walter, Albrecht, Hans, Helmut || || 14 || 31.3.-7.4. || Commissioning (Week #1) || || Clemens || Carsten || || || || || || Software || || || Walter, Albrecht, Hans, Helmut || || 15 || 7.4.-14.4. || || || || || || || 16 || 14.4.-21.4. || Commissioning (Week #2) || || Carsten || Clemens || || || || || || Software || || || Walter, Albrecht, Hans, Helmut || || 17 || 21.4.-28.4. || TBA || || || || || |
EMIR Installation and Commissioning at the IRAM 30m telescope
# |
Dates |
Main Task |
Details |
People at the 30m |
Standby in Granada |
|
|
|
|
|
Lead |
Staff |
Staff |
11 |
10.3.-17.3. |
ABCD Dismounting |
|
Santiago |
Dave, Gregorio, Pako |
|
|
|
Transport |
Truck |
Bernard |
|
|
|
|
|
Helicopter |
Javier |
|
|
12 |
17.3.-24.3. |
Installation |
|
Santiago & Bernard |
Dave |
|
|
|
|
Software |
|
|
Walter, Albrecht, Hans, Helmut |
13 |
24.3.-31.3. |
Hardware Testing & First Light |
|
Santiago & Bernard |
Dave |
|
|
|
|
Software |
|
|
Walter, Albrecht, Hans, Helmut |
14 |
31.3.-7.4. |
Commissioning (Week #1) |
|
Clemens |
Carsten |
|
|
|
|
Software |
|
|
Walter, Albrecht, Hans, Helmut |
15 |
7.4.-14.4. |
|
|
|
|
|
16 |
14.4.-21.4. |
Commissioning (Week #2) |
|
Carsten |
Clemens |
|
|
|
|
Software |
|
|
Walter, Albrecht, Hans, Helmut |
17 |
21.4.-28.4. |
TBA |
|
|
|
|
cf. also with
[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and
[http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]