EMIR Installation and Commissioning at the IRAM 30m telescope === Timeline of Installation and Commissioning at the IRAM 30m telescope ===
Line 3: Line 3:
| Week | Dates | Main Task | Details | Lead | People |
| 11 | 10.3.-17.3. | ABCD Dismounting | | SN | |
| | | Transport | | | |
| 12 | 17.3.-24.3. | EMIR Installation | | SN/BL | |
| 13 | 24.3.-31.3. | EMIR Hardware Testing & First Light | | SN/BL | |
| 14 | 31.3.-7.4. | EMIR Commissioning (Week #1) | | CT | | | |
| 15 | 7.4.-14.4. | | | | | | |
| 16 | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | |
| 17 | 21.4.-28.4. | TBA | | | | | |
 * the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here]

|| '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' ||
|| || || || || '''Lead''' || '''Staff''' || '''Staff''' ||
|||||||||||||| '''Installation Plan of SN:''' attachment:Plan001.pdf ||
|| 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || || ||
|| || || Transport || Truck/JYC:12.-15.3. || || || ||
|| || || || Helicopter/16.3. || Javier || || ||
|| || || || || || || ||
|| 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago || Jean-Yves (16.-), Bruno (16.-), Dave || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software || || Sebastien (16.-), Walter || Albrecht, Hans, Helmut ||
|| || || || || || || ||
|| 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Santiago || Jean-Yves (-26.), Anne-Laure(23.-26.), Dave || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software / Astronomy || || Sebastien (-26.), Walter, Albrecht || Hans, Helmut ||
|| || || || Operator Training || Manolo || || ||
|| || || || || || || ||
|||||||||||||| '''[https://gra-lx1.iram.es/mainWiki/EmirInstallationAndCommissioningPlan Commissioning Plan of CK]''' ||
|| 14 || 31.3.-7.4. || '''#4: Commissioning''' || || Carsten || Dirk Muders, Clemens || ||
|| || || || Software / Astronomy || || Hans + TBC || Walter, Hans, Helmut, Albrecht ||
|| || || || Operator Training || Manolo || || ||
|| || || || || || || ||
|| 15 || 7.4.-14.4. || || || || || ||
|| || || || || || || ||
|| 16 || 14.4.-21.4. || '''#5: Commissioning''' || || Carsten || Clemens, Albert || ||
|| || || || Software / Astronomy || || Helmut + TBC || Walter, Albrecht, Hans ||
|| || || || || || || ||
|| 17 || 21.4.-28.4. || TBA || || || || ||
Line 14: Line 34:
 * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and   * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule],
 * [http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule],
and
Line 16: Line 37:

The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.

Planets & Moon during Commissioning:
 * Night time: Saturn (to 60deg elev)
 * Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
 * Full moon: 9.4.

Timeline of Installation and Commissioning at the IRAM 30m telescope

#

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

Installation Plan of SN: attachment:Plan001.pdf

11

10.3.-17.3.

#1: ABCD Dismounting

Santiago

Transport

Truck/JYC:12.-15.3.

Helicopter/16.3.

Javier

12

17.3.-24.3.

#2: Installation

Santiago

Jean-Yves (16.-), Bruno (16.-), Dave

IF

Salvador, Gabriel

Software

Sebastien (16.-), Walter

Albrecht, Hans, Helmut

13

24.3.-31.3.

#3: First Light & Hardware Testing

Santiago

Jean-Yves (-26.), Anne-Laure(23.-26.), Dave

IF

Salvador, Gabriel

Software / Astronomy

Sebastien (-26.), Walter, Albrecht

Hans, Helmut

Operator Training

Manolo

[https://gra-lx1.iram.es/mainWiki/EmirInstallationAndCommissioningPlan Commissioning Plan of CK]

14

31.3.-7.4.

#4: Commissioning

Carsten

Dirk Muders, Clemens

Software / Astronomy

Hans + TBC

Walter, Hans, Helmut, Albrecht

Operator Training

Manolo

15

7.4.-14.4.

16

14.4.-21.4.

#5: Commissioning

Carsten

Clemens, Albert

Software / Astronomy

Helmut + TBC

Walter, Albrecht, Hans

17

21.4.-28.4.

TBA

cf. also with

The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.

Planets & Moon during Commissioning:

  • Night time: Saturn (to 60deg elev)
  • Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
  • Full moon: 9.4.