Differences between revisions 5 and 7 (spanning 2 versions)
Revision 5 as of 2009-02-03 10:56:11
Size: 853
Editor: visitor3
Comment:
Revision 7 as of 2009-02-03 10:59:14
Size: 950
Editor: visitor3
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:
| Week | Dates       | Main Task        | Details | Lead | People |
| 11
| 10.3.-17.3. | ABCD Dismounting |         | SN |        |
| |
| Transport |         | | |
| 12 | 17.3.-24.3. | EMIR Installation |        | SN/BL | |
| 13
| 24.3.-31.3. | EMIR Hardware Testing & First Light | | SN/BL | |
| 14
| 31.3.-7.4. | EMIR Commissioning (Week #1) | | CT | | | |
| 15 | 7.4.-14.4. |                              | | | | | |
| 16 | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | |
| 17 | 21.4.-28.4. | TBA | | | | | |
|| '''Week''' || '''Dates''' || '''Main Task''' || '''Details''' || '''Lead''' || '''People''' |
|| 11 |
| 10.3.-17.3. || ABCD Dismounting || || SN || ||
|| || |
| Transport || || || ||
|
| 12 || 17.3.-24.3. || EMIR Installation || || SN/BL || ||
|| 13 |
| 24.3.-31.3. || EMIR Hardware Testing & First Light || || SN/BL || ||
|| 14 |
| 31.3.-7.4. || EMIR Commissioning (Week #1) || || CT || || || ||
|
| 15 || 7.4.-14.4. || || || || || || ||
|
| 16 || 14.4.-21.4. || EMIR Commissioning (Week #2) || || CK || || || ||
|
| 17 || 21.4.-28.4. || TBA || || || || || ||

EMIR Installation and Commissioning at the IRAM 30m telescope

|| Week || Dates || Main Task || Details || Lead || People |

11

10.3.-17.3.

ABCD Dismounting

SN

Transport

12

17.3.-24.3.

EMIR Installation

SN/BL

13

24.3.-31.3.

EMIR Hardware Testing & First Light

SN/BL

14

31.3.-7.4.

EMIR Commissioning (Week #1)

CT

15

7.4.-14.4.

16

14.4.-21.4.

EMIR Commissioning (Week #2)

CK

17

21.4.-28.4.

TBA