Line 3: Line 3:
{{{
#!CSV
Week ; Dates ; Main Task ; Details ; People ;
11;
10.3.-17.3.; ABCD Dismounting ; ; '''SN''' ;
  ; ;
Transport ; ; ;
12;
17.3.-24.3.; EMIR Installation ; ; '''SN/BL''' ;
13; 24.3.-31.3.;
EMIR Hardware Testing & First Light ; ; '''SN/BL''' ;
14;
31.3.-7.4.; EMIR Commissioning (Week #1) ; ; CK ;
15; 7.4.-14.4.; Semana Santa ; ; ;
16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ; CK ;
17; 21.4.-28.4.; TBA ; ; ;
}}}
| Week | Dates       | Main Task        | Details | Lead | People |
| 11 |
10.3.-17.3. | ABCD Dismounting | | SN   | |
| | |
Transport        | | | |
| 12 |
17.3.-24.3. | EMIR Installation | | SN/BL | |
| 13 | 24.3.-31.3. |
EMIR Hardware Testing & First Light | | SN/BL | |
| 14 |
31.3.-7.4.  | EMIR Commissioning (Week #1) | | CT | | | |
|
15   | 7.4.-14.4.  | | | | | | |
|
16   | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | |
|
17   | 21.4.-28.4. | TBA | | | | | |

EMIR Installation and Commissioning at the IRAM 30m telescope

| Week | Dates | Main Task | Details | Lead | People | | 11 | 10.3.-17.3. | ABCD Dismounting | | SN | | | | | Transport | | | | | 12 | 17.3.-24.3. | EMIR Installation | | SN/BL | | | 13 | 24.3.-31.3. | EMIR Hardware Testing & First Light | | SN/BL | | | 14 | 31.3.-7.4. | EMIR Commissioning (Week #1) | | CT | | | | | 15 | 7.4.-14.4. | | | | | | | | 16 | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | | | 17 | 21.4.-28.4. | TBA | | | | | |