Size: 2563
Comment:
|
Size: 3276
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 1: | Line 1: |
| [https://gra-lx1.iram.es/mainWiki/EmirProject EMIR] Installation and Commissioning at the IRAM 30m telescope | === Timeline of Installation and Commissioning at the IRAM 30m telescope === * the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here] |
| Line 5: | Line 7: |
| || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || Dave, Gregorio, Pako || || || || || Transport || Truck || Bernard || || || || || || || Helicopter || Javier || || || || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago & Bernard || Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut || || 13 || 24.3.-31.3. || '''#3: Hardware Testing & First Light''' || || Santiago & Bernard || Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut || || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' (Week #1) || || Clemens || Carsten || || || || || || Software || || Albrecht || Walter, Hans, Helmut || |
|| 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || Dave, Gregorio, Pako || || || || || Transport || Truck || Jean-Yves || || || || || || || Helicopter || Javier || || || || || || || || || || || || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago/Bernard? || Jean-Yves?, Dave, Anne-Laure? || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut || || || || || || || || || || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Bernard?/Santiago || Anne-Laure?, Dave, Jean-Yves? || || || || || || IF || || || Salvador, Gabriel || || || || || Software / Astronomy || || Sebastien, Walter, Albrecht || Hans, Helmut || || || || || Operator Training || Manolo || || || || || || || || || || || || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Clemens || Carsten || || || || || || Software / Astronomy || || Hans + TBC || Walter, Hans, Helmut, Albrecht || || || || || Operator Training || Manolo || || || || || || || || || || || |
| Line 17: | Line 25: |
| || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' (Week #2) || || Carsten || Clemens || || || || || || Software || || Hans || Walter, Albrecht, Helmut || |
|| || || || || || || || || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Clemens || || || || || || Software / Astronomy || || Helmut + TBC || Walter, Albrecht, Hans || || || || || || || || || |
| Line 22: | Line 32: |
| * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and | * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule], * [http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and |
| Line 25: | Line 36: |
| The maximum number of people of the EMIR installation team at the 30m, will be '''about 6 only'''. During most of the installation period, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms. |
The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms. |
Timeline of Installation and Commissioning at the IRAM 30m telescope
the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here]
# |
Dates |
Main Task |
Details |
People at the 30m |
Standby in Granada |
|
|
|
|
|
Lead |
Staff |
Staff |
11 |
10.3.-17.3. |
#1: ABCD Dismounting |
|
Santiago |
Dave, Gregorio, Pako |
|
|
|
Transport |
Truck |
Jean-Yves |
|
|
|
|
|
Helicopter |
Javier |
|
|
|
|
|
|
|
|
|
12 |
17.3.-24.3. |
#2: Installation |
|
Santiago/Bernard? |
Jean-Yves?, Dave, Anne-Laure? |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software |
|
Sebastien, Walter |
Albrecht, Hans, Helmut |
|
|
|
|
|
|
|
13 |
24.3.-31.3. |
#3: First Light & Hardware Testing |
|
Bernard?/Santiago |
Anne-Laure?, Dave, Jean-Yves? |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software / Astronomy |
|
Sebastien, Walter, Albrecht |
Hans, Helmut |
|
|
|
Operator Training |
Manolo |
|
|
|
|
|
|
|
|
|
14 |
31.3.-7.4. |
#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] |
|
Clemens |
Carsten |
|
|
|
|
Software / Astronomy |
|
Hans + TBC |
Walter, Hans, Helmut, Albrecht |
|
|
|
Operator Training |
Manolo |
|
|
|
|
|
|
|
|
|
15 |
7.4.-14.4. |
|
|
|
|
|
|
|
|
|
|
|
|
16 |
14.4.-21.4. |
#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] |
|
Carsten |
Clemens |
|
|
|
|
Software / Astronomy |
|
Helmut + TBC |
Walter, Albrecht, Hans |
|
|
|
|
|
|
|
17 |
21.4.-28.4. |
TBA |
|
|
|
|
cf. also with
[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule],
[http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and
[http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.