Line 5: Line 5:
|| 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || Dave, Gregorio, Pako || ||
|| || || Transport || Truck || Bernard  || || ||
|| || || || Helicopter || Javier || || ||
|| 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago & Bernard || Dave || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut ||
|| 13 || 24.3.-31.3. || '''#3: Hardware Testing & First Light''' || || Santiago & Bernard || Dave || ||
|| || || || IF || || || Salvador, Gabriel ||
|| || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut ||
|| 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' ||    || Santiago || Dave, Gregorio, Pako || ||
|| || || Transport           || Truck      || Bernard || || ||
|| || ||                          || Helicopter || Javier || || ||
|| 12 || 17.3.-24.3. || '''#2: Installation'''     || || Bernard/Santiago    || Dave, Jean-Yves?, Anne-Laure? || ||
|| || ||          || IF         || || || Salvador, Gabriel ||
|| || ||          || Software   || || Sebastien, Walter || Albrecht, Hans, Helmut ||
|| 13 || 24.3.-31.3. || '''#3: Hardware Testing & First Light'''|| || Santiago/Bernard || Dave, Jean-Yves?, Anne-Laure? || ||
|| || ||          || IF || || || Salvador, Gabriel ||
|| || ||          || Software || || Sebastien, Walter || Albrecht, Hans, Helmut ||
Line 25: Line 25:
The maximum number of people of the EMIR installation team at the 30m, will be '''about 6 only'''.
During most of the installation period, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD.
Juan, two operators, and two cooks will be at the site, with 14 bedrooms.
The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.

[https://gra-lx1.iram.es/mainWiki/EmirProject EMIR] Installation and Commissioning at the IRAM 30m telescope

#

Dates

Main Task

Details

People at the 30m

Standby in Granada

Lead

Staff

Staff

11

10.3.-17.3.

#1: ABCD Dismounting

Santiago

Dave, Gregorio, Pako

Transport

Truck

Bernard

Helicopter

Javier

12

17.3.-24.3.

#2: Installation

Bernard/Santiago

Dave, Jean-Yves?, Anne-Laure?

IF

Salvador, Gabriel

Software

Sebastien, Walter

Albrecht, Hans, Helmut

13

24.3.-31.3.

#3: Hardware Testing & First Light

Santiago/Bernard

Dave, Jean-Yves?, Anne-Laure?

IF

Salvador, Gabriel

Software

Sebastien, Walter

Albrecht, Hans, Helmut

14

31.3.-7.4.

#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #1)

Clemens

Carsten

Software

Albrecht

Walter, Hans, Helmut

15

7.4.-14.4.

16

14.4.-21.4.

#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #2)

Carsten

Clemens

Software

Hans

Walter, Albrecht, Helmut

17

21.4.-28.4.

TBA

cf. also with

The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.