[https://gra-lx1.iram.es/mainWiki/EmirProject EMIR] Installation and Commissioning at the IRAM 30m telescope
# |
Dates |
Main Task |
Details |
People at the 30m |
Standby in Granada |
|
|
|
|
|
Lead |
Staff |
Staff |
11 |
10.3.-17.3. |
ABCD Dismounting |
|
Santiago |
Dave, Gregorio, Pako |
|
|
|
Transport |
Truck |
Bernard |
|
|
|
|
|
Helicopter |
Javier |
|
|
12 |
17.3.-24.3. |
Installation |
|
Santiago & Bernard |
Dave |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software |
|
Sebastien, Walter |
Albrecht, Hans, Helmut |
13 |
24.3.-31.3. |
Hardware Testing & First Light |
|
Santiago & Bernard |
Dave |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software |
|
Sebastien, Walter |
Albrecht, Hans, Helmut |
14 |
31.3.-7.4. |
[https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #1) |
|
Clemens |
Carsten |
|
|
|
|
Software |
|
|
Walter, Albrecht, Hans, Helmut |
15 |
7.4.-14.4. |
|
|
|
|
|
16 |
14.4.-21.4. |
[https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #2) |
|
Carsten |
Clemens |
|
|
|
|
Software |
|
|
Walter, Albrecht, Hans, Helmut |
17 |
21.4.-28.4. |
TBA |
|
|
|
|
cf. also with
[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and
[http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]
The maximum number of people of the EMIR installation team at the 30m, will be about 6 only. During most of the installation period, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.