| EMIR Installation and Commissioning at the IRAM 30m telescope | === Timeline of Installation and Commissioning at the IRAM 30m telescope === | 
| Line 3: | Line 3: | 
| {{{ #!CSV Week ; Dates ; Main Task ; Details ; Lead ; People ; 11;10.3.-17.3.; ABCD Dismounting ; ; SN ; ; ; Transport ; ; ; 12; 17.3.-24.3.; EMIR Installation ; ; SN/BL ; 13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ; SN/BL ; 14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ; CK ; ; 15; 7.4.-14.4.; Semana Santa ; ; ; ; 16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ; CK ; ; 17; 21.4.-28.4.; TBA ; ; ; ; }}} | * the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here] || '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' || || || || || || '''Lead''' || '''Staff''' || '''Staff''' || |||||||||||||| '''Installation Plan of SN:''' attachment:Plan001.pdf || || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || || || || || || Transport || Truck/JYC:12.-15.3. || || || || || || || || Helicopter/16.3. || Javier || || || || || || || || || || || || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago || Jean-Yves (16.-), Bruno (16.-), Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien (16.-), Walter || Albrecht, Hans, Helmut || || || || || || || || || || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Santiago || Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-27.3.)???|| || || || || || IF || || || Salvador, Gabriel || || || || || Software / Astronomy || || Sebastien (-26.), Walter, Albrecht, Clemens (28.3.-) || Hans, Helmut, Juan for the weekend || || || || || Operator Training || Manolo || || || || || || || || || || || |||||||||||||| '''[https://gra-lx1.iram.es/mainWiki/EmirInstallationAndCommissioningPlan Commissioning Plan of CK]''' || || 14 || 31.3.-7.4. || '''#4: Commissioning''' || || Carsten || Dirk Muders, Clemens (-3.4.) || || || || || || Software / Astronomy || || Hans + TBC || Walter, Hans, Helmut, Albrecht || || || || || Operator Training || Manolo || || || || || || || || || || || || 15 || 7.4.-14.4. || || || || || || || || || || || || || || || 16 || 14.4.-21.4. || '''#5: Commissioning''' || || Carsten || Clemens, Albert || || || || || || Software / Astronomy || || Helmut + TBC || Walter, Albrecht, Hans || || || || || || || || || || 17 || 21.4.-28.4. || TBA || || || || || cf. also with * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule], * [http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations] The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms. Planets & Moon during Commissioning: * Night time: Saturn (to 60deg elev) * Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter * Full moon: 9.4. | 
Timeline of Installation and Commissioning at the IRAM 30m telescope
- the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here] 
| # | Dates | Main Task | Details | People at the 30m | Standby in Granada | |
| 
 | 
 | 
 | 
 | Lead | Staff | Staff | 
| Installation Plan of SN: attachment:Plan001.pdf | ||||||
| 11 | 10.3.-17.3. | #1: ABCD Dismounting | 
 | Santiago | 
 | 
 | 
| 
 | 
 | Transport | Truck/JYC:12.-15.3. | 
 | 
 | 
 | 
| 
 | 
 | 
 | Helicopter/16.3. | Javier | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 12 | 17.3.-24.3. | #2: Installation | 
 | Santiago | Jean-Yves (16.-), Bruno (16.-), Dave | 
 | 
| 
 | 
 | 
 | IF | 
 | 
 | Salvador, Gabriel | 
| 
 | 
 | 
 | Software | 
 | Sebastien (16.-), Walter | Albrecht, Hans, Helmut | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 13 | 24.3.-31.3. | #3: First Light & Hardware Testing | 
 | Santiago | Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-27.3.)??? | 
 | 
| 
 | 
 | 
 | IF | 
 | 
 | Salvador, Gabriel | 
| 
 | 
 | 
 | Software / Astronomy | 
 | Sebastien (-26.), Walter, Albrecht, Clemens (28.3.-) | Hans, Helmut, Juan for the weekend | 
| 
 | 
 | 
 | Operator Training | Manolo | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| [https://gra-lx1.iram.es/mainWiki/EmirInstallationAndCommissioningPlan Commissioning Plan of CK] | ||||||
| 14 | 31.3.-7.4. | #4: Commissioning | 
 | Carsten | Dirk Muders, Clemens (-3.4.) | 
 | 
| 
 | 
 | 
 | Software / Astronomy | 
 | Hans + TBC | Walter, Hans, Helmut, Albrecht | 
| 
 | 
 | 
 | Operator Training | Manolo | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 15 | 7.4.-14.4. | 
 | 
 | 
 | 
 | 
 | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 16 | 14.4.-21.4. | #5: Commissioning | 
 | Carsten | Clemens, Albert | 
 | 
| 
 | 
 | 
 | Software / Astronomy | 
 | Helmut + TBC | Walter, Albrecht, Hans | 
| 
 | 
 | 
 | 
 | 
 | 
 | 
 | 
| 17 | 21.4.-28.4. | TBA | 
 | 
 | 
 | 
 | 
cf. also with
- [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule], 
- [http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and 
- [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations] 
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.
Planets & Moon during Commissioning:
- Night time: Saturn (to 60deg elev)
- Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
- Full moon: 9.4.