| EMIR Installation and Commissioning at the IRAM 30m telescope | === Timeline of Installation and Commissioning at the IRAM 30m telescope === | 
| Line 3: | Line 3: | 
| {{{ #!CSV Week ; Dates ; Main Task ; Details ; Lead ; People ; 11;10.3.-17.3.; ABCD Dismounting ; ; SN ; ; ; Transport ; ; ; 12; 17.3.-24.3.; EMIR Installation ; ; SN/BL ; 13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ; SN/BL ; 14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ; CK ; ; 15; 7.4.-14.4.; Semana Santa ; ; ; ; 16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ; CK ; ; 17; 21.4.-28.4.; TBA ; ; ; ; }}}  | 
 * the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here] || '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' || || || || || || '''Lead''' || '''Staff''' || '''Staff''' || || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || Dave, Gregorio, Pako || || || || || Transport || Truck/JYC:12.-15.3. || || || || || || || || Helicopter/JL:16.3. || || || || || || || || || || || || || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago || Jean-Yves, Bruno, Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut || || || || || || || || || || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing'''|| || Santiago || Jean-Yves, Anne-Laure(23.-31.), Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software / Astronomy || || Sebastien, Walter, Albrecht || Hans, Helmut || || || || || Operator Training || Manolo || || || || || || || || || || || || 14 || 31.3.-7.4. || '''#4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Clemens || Carsten || || || || || || Software / Astronomy || || Hans + TBC || Walter, Hans, Helmut, Albrecht || || || || || Operator Training || Manolo || || || || || || || || || || || || 15 || 7.4.-14.4. || || || || || || || || || || || || || || || 16 || 14.4.-21.4. || '''#5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]''' || || Carsten || Clemens || || || || || || Software / Astronomy || || Helmut + TBC || Walter, Albrecht, Hans || || || || || || || || || || 17 || 21.4.-28.4. || TBA || || || || || cf. also with * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule], * [http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations] The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms. Planets & Moon during Commissioning: * Night time: Saturn (to 60deg elev) * Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter * Full moon: 9.4.  | 
Timeline of Installation and Commissioning at the IRAM 30m telescope
the EMIR homepage for IRAM staff is [https://gra-lx1.iram.es/mainWiki/EmirProject here]
#  | 
  Dates  | 
  Main Task  | 
  Details  | 
  People at the 30m  | 
  Standby in Granada  | 
|
  | 
  
  | 
  
  | 
  
  | 
  Lead  | 
  Staff  | 
  Staff  | 
11  | 
  10.3.-17.3.  | 
  #1: ABCD Dismounting  | 
  
  | 
  Santiago  | 
  Dave, Gregorio, Pako  | 
  
  | 
  | 
  
  | 
  Transport  | 
  Truck/JYC:12.-15.3.  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  Helicopter/JL:16.3.  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
12  | 
  17.3.-24.3.  | 
  #2: Installation  | 
  
  | 
  Santiago  | 
  Jean-Yves, Bruno, Dave  | 
  
  | 
  | 
  
  | 
  
  | 
  IF  | 
  
  | 
  
  | 
  Salvador, Gabriel  | 
  | 
  
  | 
  
  | 
  Software  | 
  
  | 
  Sebastien, Walter  | 
  Albrecht, Hans, Helmut  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
13  | 
  24.3.-31.3.  | 
  #3: First Light & Hardware Testing  | 
  
  | 
  Santiago  | 
  Jean-Yves, Anne-Laure(23.-31.), Dave  | 
  
  | 
  | 
  
  | 
  
  | 
  IF  | 
  
  | 
  
  | 
  Salvador, Gabriel  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  Sebastien, Walter, Albrecht  | 
  Hans, Helmut  | 
  | 
  
  | 
  
  | 
  Operator Training  | 
  Manolo  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
14  | 
  31.3.-7.4.  | 
  #4: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]  | 
  
  | 
  Clemens  | 
  Carsten  | 
  
  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  Hans + TBC  | 
  Walter, Hans, Helmut, Albrecht  | 
  | 
  
  | 
  
  | 
  Operator Training  | 
  Manolo  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
15  | 
  7.4.-14.4.  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
16  | 
  14.4.-21.4.  | 
  #5: [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning]  | 
  
  | 
  Carsten  | 
  Clemens  | 
  
  | 
  | 
  
  | 
  
  | 
  Software / Astronomy  | 
  
  | 
  Helmut + TBC  | 
  Walter, Albrecht, Hans  | 
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
  
  | 
17  | 
  21.4.-28.4.  | 
  TBA  | 
  
  | 
  
  | 
  
  | 
  
  | 
cf. also with
[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule],
[http://www.iram.es/IRAMES/groups/operator/opesched.htm Operator Schedule], and
[http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.
Planets & Moon during Commissioning:
- Night time: Saturn (to 60deg elev)
 - Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
 - Full moon: 9.4.
 