Week ; Dates ; Main Task ; Details ; Lead ; People ;
11;
10.3.-17.3.; ABCD Dismounting ; ; SN ;
  ; ;
Transport ; ; ;
12; 17.3.-24.3.; EMIR Installation ; ; SN/BL ;
13;
24.3.-31.3.; EMIR Hardware Testing & First Light ; ; SN/BL ;
14;
31.3.-7.4.; EMIR Commissioning (Week #1) ; ; CK ; ;
15; 7.4.-14.4.; Semana Santa ; ; ; ;
16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ; CK ; ;
17; 21.4.-28.4.; TBA ; ; ; ;
}}}
| Week | Dates       | Main Task        | Details | Lead | People |
| 11 |
10.3.-17.3. | ABCD Dismounting | | SN   | |
| | |
Transport        | | | |
|
12   | 17.3.-24.3. | EMIR Installation | | SN/BL | |
| 13 |
24.3.-31.3. | EMIR Hardware Testing & First Light | | SN/BL | |
| 14 |
31.3.-7.4.  | EMIR Commissioning (Week #1) | | CT | | | |
|
15   | 7.4.-14.4.  | | | | | | |
|
16   | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | |
|
17   | 21.4.-28.4. | TBA | | | | | |

cf. also with
 * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and
 * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]

EMIR Installation and Commissioning at the IRAM 30m telescope

| Week | Dates | Main Task | Details | Lead | People | | 11 | 10.3.-17.3. | ABCD Dismounting | | SN | | | | | Transport | | | | | 12 | 17.3.-24.3. | EMIR Installation | | SN/BL | | | 13 | 24.3.-31.3. | EMIR Hardware Testing & First Light | | SN/BL | | | 14 | 31.3.-7.4. | EMIR Commissioning (Week #1) | | CT | | | | | 15 | 7.4.-14.4. | | | | | | | | 16 | 14.4.-21.4. | EMIR Commissioning (Week #2) | | CK | | | | | 17 | 21.4.-28.4. | TBA | | | | | |

cf. also with

EmirPlanning (last edited 2009-11-17 08:30:21 by lt-ck)