Week ; Dates ; Main Task ; Details ; Lead ; People ;
11;10.3.-17.3.; ABCD Dismounting ; ; SN ;
  ; ; Transport ; ; ;
12; 17.3.-24.3.; EMIR Installation ; ; SN/BL ;
13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ; SN/BL ;
14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ; CK ; ;
15; 7.4.-14.4.; Semana Santa ; ; ; ;
16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ; CK ; ;
17; 21.4.-28.4.; TBA ; ; ; ;
Week ; Dates ; Main Task ; Details ; People ;
11;10.3.-17.3.; ABCD Dismounting ; ; '''SN''' ;
  ; ; Transport ; ; ; 
12; 17.3.-24.3.; EMIR Installation ; ; '''SN/BL''' ;
13; 24.3.-31.3.; EMIR Hardware Testing & First Light ; ; '''SN/BL''' ;
14; 31.3.-7.4.; EMIR Commissioning (Week #1) ; ; CK ;
15; 7.4.-14.4.; Semana Santa ; ; ;
16; 14.4.-21.4.; EMIR Commissioning (Week #2) ; ; CK ;
17; 21.4.-28.4.; TBA ; ; ;
Line 15: Line 15:

cf. also with
 * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and
 * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations]

EMIR Installation and Commissioning at the IRAM 30m telescope

Week Dates Main Task Details People
11 10.3.-17.3. ABCD Dismounting '''SN'''
Transport
12 17.3.-24.3. EMIR Installation '''SN/BL'''
13 24.3.-31.3. EMIR Hardware Testing & First Light '''SN/BL'''
14 31.3.-7.4. EMIR Commissioning (Week #1) CK
15 7.4.-14.4. Semana Santa
16 14.4.-21.4. EMIR Commissioning (Week #2) CK
17 21.4.-28.4. TBA