EMIR Installation and Commissioning at the IRAM 30m telescope | === Timeline of Installation and Commissioning at the IRAM 30m telescope === * the EMIR homepage for IRAM staff is [[https://gra-lx1.iram.es/mainWiki/EmirProject|here]] || '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' || || || || || || '''Lead''' || '''Staff''' || '''Staff''' || ||||||||||||||<style="text-align: center;"> || || 11 || 10.3.-17.3. || '''#1: ABCD Dismounting''' || || Santiago || || || || || || Transport || Truck/JYC:12.-15.3. || || || || || || || || Helicopter/16.3. || Javier || || || || || || || || || || || || 12 || 17.3.-24.3. || '''#2: Installation''' || || Santiago || Jean-Yves (16.-), Bruno (16.-), Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien (16.-), Walter || Albrecht, Hans, Helmut || || || || || || || || || || 13 || 24.3.-31.3. || '''#3: First Light & Hardware Testing''' || || Santiago || Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-26.3.), Juan(23.,24.,27.3.-2.4.) || || || || || || IF || || || Salvador, Gabriel || || || || || Software / Astronomy || || Sebastien(-26.), Walter, Albrecht, Clemens(27.3.-) || Hans, Helmut || || || || || Operator Training || Manolo || || || || || || || || || || || ||||||||||||||<style="text-align: center;"> || || 14 || 31.3.-7.4. || '''#4: Commissioning''' || || Carsten || Dirk Muders, Sascha Trippe, Juan(27.3.-Thu), Denise(Fri-Mon) || || || || || || Software / Astronomy || || Hans, Clemens(-Fri), Helmut(Tue-Fri) || Walter, Albrecht, Gabriel || || || || || Operator Training || Manolo || || || || || || || || || || || || 15 || 7.4.-14.4. || 24 hours MAMBO2 pooled observations & Full Moon with EMIR || || || Breezy Ocana Flaquer(Mon-Tue) || || || || || || || || || || || 16 || 14.4.-21.4. || '''#5: Commissioning''' || || Carsten(Di-Mo) || Clemens(Di-Mo), Albert(Di-Mo), Melanie, Karl(Thu-Sun), Rebeca(Fri-Mon), Gabriel(Thu-Fri) || || || || || || Software / Astronomy || || || Helmut, Walter, Albrecht, Hans || || || || || || || || || || 17 || 21.4.-28.4. || '''#6: Commissioning & MAMBO Pool Observations''' || || Hans(EMIR), Denise(MAMBO), Albrecht(Mo-Di) || || Helmut, Gabriel || |
Line 3: | Line 31: |
|| '''#''' || '''Dates''' || '''Main Task''' || '''Details''' ||||<style="text-align: center;">'''People at the 30m''' || '''Standby in Granada''' || || || || || || '''Lead''' || '''Staff''' || '''Staff''' || || 11 || 10.3.-17.3. || ABCD Dismounting || || Santiago || Dave, Gregorio, Pako || || || || || Transport || Truck || Bernard || || || || || || || Helicopter || Javier || || || || 12 || 17.3.-24.3. || Installation || || Santiago & Bernard || Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut || || 13 || 24.3.-31.3. || Hardware Testing & First Light || || Santiago & Bernard || Dave || || || || || || IF || || || Salvador, Gabriel || || || || || Software || || Sebastien, Walter || Albrecht, Hans, Helmut || || 14 || 31.3.-7.4. || [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #1) || || Clemens || Carsten || || || || || || Software || || || Walter, Albrecht, Hans, Helmut || || 15 || 7.4.-14.4. || || || || || || || 16 || 14.4.-21.4. || [https://gra-lx1.iram.es/mainWiki/EmirCommissioningPlan Commissioning] (Week #2) || || Carsten || Clemens || || || || || || Software || || || Walter, Albrecht, Hans, Helmut || || 17 || 21.4.-28.4. || TBA || || || || || |
cf. also with |
Line 21: | Line 33: |
cf. also with * [http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule AoD Schedule] and * [http://www.iram.es/IRAMES/mainWiki/PoolW0809 schedule of MAMBO pooled observations] |
* [[http://www.iram.es/IRAMES/mainWiki/AstronomerOnDutySchedule|AoD Schedule]], * [[http://www.iram.es/IRAMES/groups/operator/opesched.htm|Operator Schedule]], and * [[http://www.iram.es/IRAMES/mainWiki/PoolW0809|schedule of MAMBO pooled observations]] The maximum number of people of the EMIR installation team at the 30m, will be '''~6 during EMIR weeks #1-3 and ~8 during weeks #4-5'''. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms. |
Line 25: | Line 38: |
The maximum number of people of the EMIR installation team at the 30m, will be '''about 6 only'''. During most of the installation period, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms. |
Planets & Moon during Commissioning: * Night time: Saturn (to 60deg elev) * Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter * Full moon: 9.4. |
Timeline of Installation and Commissioning at the IRAM 30m telescope
the EMIR homepage for IRAM staff is here
# |
Dates |
Main Task |
Details |
People at the 30m |
Standby in Granada |
|
|
|
|
|
Lead |
Staff |
Staff |
|
||||||
11 |
10.3.-17.3. |
#1: ABCD Dismounting |
|
Santiago |
|
|
|
|
Transport |
Truck/JYC:12.-15.3. |
|
|
|
|
|
|
Helicopter/16.3. |
Javier |
|
|
|
|
|
|
|
|
|
12 |
17.3.-24.3. |
#2: Installation |
|
Santiago |
Jean-Yves (16.-), Bruno (16.-), Dave |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software |
|
Sebastien (16.-), Walter |
Albrecht, Hans, Helmut |
|
|
|
|
|
|
|
13 |
24.3.-31.3. |
#3: First Light & Hardware Testing |
|
Santiago |
Jean-Yves (-26.), Anne-Laure(23.-26.), Dave, Bernard(23.-26.3.), Juan(23.,24.,27.3.-2.4.) |
|
|
|
|
IF |
|
|
Salvador, Gabriel |
|
|
|
Software / Astronomy |
|
Sebastien(-26.), Walter, Albrecht, Clemens(27.3.-) |
Hans, Helmut |
|
|
|
Operator Training |
Manolo |
|
|
|
|
|
|
|
|
|
|
||||||
14 |
31.3.-7.4. |
#4: Commissioning |
|
Carsten |
Dirk Muders, Sascha Trippe, Juan(27.3.-Thu), Denise(Fri-Mon) |
|
|
|
|
Software / Astronomy |
|
Hans, Clemens(-Fri), Helmut(Tue-Fri) |
Walter, Albrecht, Gabriel |
|
|
|
Operator Training |
Manolo |
|
|
|
|
|
|
|
|
|
15 |
7.4.-14.4. |
24 hours MAMBO2 pooled observations & Full Moon with EMIR |
|
|
Breezy Ocana Flaquer(Mon-Tue) |
|
|
|
|
|
|
|
|
16 |
14.4.-21.4. |
#5: Commissioning |
|
Carsten(Di-Mo) |
Clemens(Di-Mo), Albert(Di-Mo), Melanie, Karl(Thu-Sun), Rebeca(Fri-Mon), Gabriel(Thu-Fri) |
|
|
|
|
Software / Astronomy |
|
|
Helmut, Walter, Albrecht, Hans |
|
|
|
|
|
|
|
17 |
21.4.-28.4. |
#6: Commissioning & MAMBO Pool Observations |
|
Hans(EMIR), Denise(MAMBO), Albrecht(Mo-Di) |
|
Helmut, Gabriel |
cf. also with
The maximum number of people of the EMIR installation team at the 30m, will be ~6 during EMIR weeks #1-3 and ~8 during weeks #4-5. During EMIR weeks #1-3, MAMBO pooled observations are scheduled during night time, with two observers, plus AoD. Juan, two operators, and two cooks will be at the site, with 14 bedrooms.
Planets & Moon during Commissioning:
- Night time: Saturn (to 60deg elev)
- Day time: Mars (4.3" diameter, to ~45deg elevation), Uranus (to 45deg Elevation), Venus, Jupiter
- Full moon: 9.4.